Deduction V2 — progress 2026-07-17
Delivery / Program Management — periodic status report.
health:carries the delivery-health status; the doc-lifecyclestatus:stays in the linter enum (active).
Progress
progress_done_days: 13 · progress_pct: 81 · progress_total_days: 16
The hub_core hold/settlement engine is code-complete — all 7 backend tasks (T1–T7) are Done and merged (13 / 13 md). Today (2026-07-17) BIF-8824 stakeholder sign-off was also marked Done, so the engine slice is substantively closed. The initiative-level denominator is 16 md (13 BE + 3 QA), yielding 81%.
- T1–T7 are code-corroborated in
hub_core(T1–T6) andhub-worker(T7): BIF-8740/8741/8742/8743/8744/8745/8746. - T1 specifically maps to
hub_corePR #8049, sha070b20de02(per the task-breakdown line 67). - BIF-8824 (stakeholder sign-off) is code-free and Done today.
Denominator revision: the 2026-07-15 entry recorded 26.5 md because DED-S07/S08 (modpanel UI) had been re-scoped into the initiative. That Modpanel UI re-scope did not survive; the authoritative task-breakdown grand total is 16 md (13 BE + 3 QA) per line 50 of deduction-v2.task-breakdown.md. The 3 QA md are not yet in sprint / have no independent evidence, so the initiative is not at 100%.
Evidence
hub_corePR #8049, sha070b20de02(T1 hold ledger schema, BIF-8740)hub_corePR #8050 (T2 create hold at send, BIF-8741)hub_corePR #8051 (T3 available-balance helper, BIF-8742)hub_corePR #8087 (T4 webhook transitions, BIF-8743)hub_corePR #8088 (T5 EOD settlement, BIF-8744)hub_corePR #8092 (T6 stale-hold sweeper, BIF-8745)hub-workersha8584f122(T7 cron scheduling, BIF-8746)- BIF-8824 stakeholder sign-off — code-free, Done 2026-07-17
- Pass narrative:
bifrost/delivery/reconciliations/2026-07-06-sprint-01/2026-07-17-pass-07.md