Bifrost Sprint 1 (2026-Q3) — Jira reconciliation, pass 10 (2026-07-21, CLOSE)
Jira reconciliation — recheck (2026-07-21, pass 10 — sprint close)
This is the close pass of record (sprint_end 2026-07-20; pulled 2026-07-21 00:xx). Fresh full
pull of sprint 21367 via MCP → digest (147 issues, +5 vs pass 9's 142) → offline
sprint:reconcile --digest. Vitals: 85 done · 15 WIP · 47 To Do; 10 done since 2026-07-19;
oldest in-progress BIF-8570 (created 2026-06-17, ~34 days, Syafrizal M.). Code-evidence caveat:
only hub-chat exists as a sibling checkout in this session — the 2026-07-19 post-close
corroboration file (qontak-billing/report-worker/hub-core/hub-service walk) is cited as evidence
where this pass could not re-search; all such citations are marked PARTIAL.
Material changes since pass 9 (all board-evidenced):
- Self Top-up (P3) functionally closed on the board: BIF-8773 (QA retest, closes BIF-8382) Done, resolved 2026-07-20. New bugs BIF-8844/BIF-8845 are tracked as Sprint-2 work (Sprint 2 plan, Madani #2 / Yoddi #3). The 2026-07-20 dated status already records this.
- Qontak One Team (P4): all 10 in-sprint BIF-8642 issues Done — BIF-8864/8865/8866 (BE
Launchpad endpoints) resolved 2026-07-19/20. Engine flags
health: at-riskvs all-done (see F-18). - Self-Subs (P6): BIF-8802 (Task 2.2 hub-service half) Done, resolved 2026-07-20.
- Quota Management (P9): first Done — BIF-8715 resolved 2026-07-20; 8 children remain To Do (F-22 movement).
- Adhoc bucket: BIF-8940 Done 2026-07-20 (Grehasta); A9's substantive FE cluster BIF-8829–8833 sits Ready to Merged / In Deployment while parent Story BIF-8682 stays To Do (F-16).
Status of prior findings (by id):
- F-4 (
off-plan-load) — ⛔ ESCALATED, STILL OPEN at close (9 passes): BIF-8570 In Progress 34 days, oldest WIP team-wide. ADR 0001-second-fe-engineer-decision.md stillproposal/dri: TBD. Owner: Bifrost EM/TPM — the ADR was required as a Sprint 2 planning input and is now overdue; decide within Sprint 2 week 1. Carried to Sprint 2. - F-7 (
forecast-at-risk) — CLOSED at close as a confirmed forecast miss: A2 (BIF-8751) absent from sprint 21367 through the entire window (not in the 147-issue close digest). The formal carry note is this close's## Sprint review(Carried over) + Sprint 2's Satya #3 PULL-TO-CLOSE row. No further Sprint-1 action. - F-8 (
off-plan-load) — STILL OPEN, grew again: BIF-8757 now 30 in-sprint issues (15 done / 4 WIP / 11 To Do; was 27 at pass 8). Owner: TPM — the tracked-bucket-container decision is still owed; carried to Sprint 2. - F-10 (
coverage-gap) — CLOSED at close as a confirmed outcome: P13 (BIF-8658), P14 (BIF-8640), P16 (BIF-8641) ended the sprint at zero board presence; P15 (BIF-8659) likewise (its 4 tasks BIF-8852–8855 are in Sprint 2/21464 instead). Recorded in Carried over; Sprint 2 queues these deliberately (Satya #2, Hafriz #3/#4, Syafrizal #8/#9). - F-13 (
code-evidence-gap) — RESOLVED (2026-07-19 post-close corroboration): BIF-8803 and BIF-8804 were genuine redirects (BIF-8792/BIF-8793), code-verified merged. - F-14 (
code-evidence-gap) — STILL OPEN, but downgraded: BIF-8708/8709 still show zero code trace inhub-chat(re-searched this pass; hub-core/qontak-billing not searchable — PARTIAL). New mitigating evidence: retest BIF-8773 passed and closed 2026-07-20, so the fixes are functionally verified even without a located diff. Owner: Madani — one-line confirmation of where the fix landed (config/seed-data vs code repo) closes this. Carried to Sprint 2. - F-15 (scope question) — STILL OPEN at close: BIF-7825 (Done 2026-07-07) maps to no
breakdown task; BIF-8760 (Task 4 FE) ended the sprint
Ready to Test, not Done. Owner: TPM; Sales Invoice + Jurnal progress stays held. Carried (Sprint 2 Syafrizal #3, Yoddi #5). - F-16 (
bucket-tracker-drift) — ⛔ ESCALATED, STILL OPEN: A9 parent Story BIF-8682 still To Do (assignee Addo) while children BIF-8880 (FE) + BIF-8876 (QA) are Done and the follow-on FE cluster BIF-8829–8833 is Ready to Merged / In Deployment. Owner: Addo (PM) — close BIF-8682 or state why not; board fix only. - F-17 (
bucket-tracker-drift) — STILL OPEN: A11 / BIF-8612 stillWaiting Confirmation, unassigned. Owner: TPM — confirm the Expedite classification + name an authorizer (open ask since 2026-07-14). - F-18 (
blocked-done-conflict) — movement, STILL OPEN (decision only): all 10 BIF-8642 issues Done; engine:health: at-risk→ jira-implied complete. The 2026-07-20 dated status exists. Owner: Addo/TPM — confirm initiative completion (or name the remainder: BIF-8911 QA + Tasks 7–8 are Sprint-2 scope per its plan) and update READMEhealth:accordingly. - F-19 (
epic-wiring-drift) — ⛔ ESCALATED, STILL OPEN: 9 off-map parent Epics at close (BIF-7803 ×12, BIF-8101 ×8, BIF-8757 ×30, BIF-7795 ×1, BIF-8869 ×2, BIF-8293 ×3, BIF-7792 ×1, BIF-7550 ×1, BIF-7949 ×3). Owner: TPM → runjira-alignment-check(already owed since pass 7). - F-22 (
coverage-gap, P9 half) — STILL OPEN with first movement: BIF-8715 Done 2026-07-20; 8 To Do remain. Confirmed startable — Sprint 2 Madani #4 owns T1–T8. Carried.
New findings from the 2026-07-21 close pull: none material beyond the taxonomy rows already
carried above. Two engine blocked-done-conflict rows (lite-seats on-track vs 4/4 sprint issues
Done; meta-whatsapp-pricing at-risk vs 5/5 Done) are informational, not conflicts — both
initiatives have known non-sprint remainders (Lite Seats 2.3/2.8 externally blocked; Meta Pricing
Phase 2 gated on the pricing decision + real-WABA validation). Three engine assignment-drift
rows (+Addo assigned on deduction-v2 / qontak-one-team / self-topup issues) resolve per
roster.json: Addo is PM — routes to a TPM read, not a staffing-mirror edit.
Per "captures, never estimates": this pass proposes no new man-day writes — the 2026-07-20 dated status entries (written during Sprint 2 pass 01 propagation) remain the latest evidenced burnups; nothing done since then changes a corroborated sum except items already recorded there.
Downstream propagation worklist (this pass)
| # | Finding | Canonical artifact to reconcile | Owning tool / skill |
|---|---|---|---|
| 1 | F-4 | ADR 0001 decision (dri, verdict) | EM/TPM decision — Sprint 2 week 1 |
| 2 | F-8 / F-19 | Jira Epic wiring / bucket container | jira-alignment-check |
| 3 | F-14 | Madani confirmation → board note; no repo edit | assignee/TPM (board fix) |
| 4 | F-16 | BIF-8682 board close | Addo (board fix) |
| 5 | F-17 | BIF-8612 classification + authorizer | TPM |
| 6 | F-18 | qontak-one-team README health: after completion decision | TPM + lint:delivery |
| 7 | Sprint doc | status: archived, final review | this close pass |