Self-Subs

The prior 0.5 / 17.5 day snapshot is withheld because its denominator predates the scope changes. The following Jira-Done candidates were corroborated on production branches but remain uncredited until the task map and discipline estimates are reconciled:

Jira issueCandidate effortMerged-code evidence
BIF-87900.5 BE mdhub-core PR #8007 / 9581b9ebe0
BIF-8791~0.75 BE mdhub-core PR #8020 / 1a6e2a5a7c
BIF-8792~1 BE mdhub-service PR #3055 / a2e237fc8; hub-core PR #8022 / 63143e8c6c
BIF-8793~1 BE mdhub-service PR #3056 / ada19b041; hub-core d3afe1ce8f; moderator-be PR #2345 / e454ff13
BIF-8802~0.25 BE mdhub-service PR #3061 / 9b8350077

BIF-8803/BIF-8804 are Won't Fix; BIF-8970 is In Review; PXL-9379 is outside the current FE/BE/QA estimate. None receives completion credit in this pass.

Sales Invoice + Jurnal

BIF-8775, BIF-8841, BIF-8842, BIF-8893, and BIF-8947 are board-complete but had no merged-code corroboration in this run. They remain excluded, leaving progress at 0 / 6.5 days.

Meta x Modpanel Call Usage

BIF-8972 is Ready to Test; no completed, code-corroborated sprint task was confirmed. Progress remains 0 / 15.5 days.

Qontak One Team

The original slice remains 12.5 / 15.5 days (81%). BIF-8968 is the corroborated completed ticket in this snapshot; BIF-9068 is in progress and receives no completion credit.