Lite Seats — Status 2026-07-16
Progress derived by
sprint-resyncpass 6 (2026-07-16, sprint 21367, step-6b computed proposal).
Summary
First measurable progress: 0% → 13% (3.0 / 22.5 md). Four Phase-2 BE tasks landed this sprint, all done and code-corroborated (4/4).
Progress
progress_done_days = 3.0 of effort_total_days = 22.5 → 13%.
| Done task | Jira | Effort | Code evidence |
|---|---|---|---|
| Task 2.1 — consumed_bucket migration + SQLC queries | BIF-8848 | 1.0 BE | corroborated |
| Task 2.2 — lite_config table (inbox blocklist + permission cap) | BIF-8849 | 1.0 BE | corroborated |
| Task 2.4 — Feature-flag read via qontak-preferences | BIF-8850 | 0.5 BE | corroborated |
| Task 2.5 — Shared Redis lock helper | BIF-8851 | 0.5 BE | corroborated |
Remaining: 19.5 md (BE 10 + FE 4 + QA 4.5 — Tasks 1.1, 1.2, 2.3, 2.6-2.10 not started).