Lite Seats — Status 2026-07-16

Progress derived by sprint-resync pass 6 (2026-07-16, sprint 21367, step-6b computed proposal).

Summary

First measurable progress: 0% → 13% (3.0 / 22.5 md). Four Phase-2 BE tasks landed this sprint, all done and code-corroborated (4/4).

Progress

progress_done_days = 3.0 of effort_total_days = 22.513%.

Done taskJiraEffortCode evidence
Task 2.1 — consumed_bucket migration + SQLC queriesBIF-88481.0 BEcorroborated
Task 2.2 — lite_config table (inbox blocklist + permission cap)BIF-88491.0 BEcorroborated
Task 2.4 — Feature-flag read via qontak-preferencesBIF-88500.5 BEcorroborated
Task 2.5 — Shared Redis lock helperBIF-88510.5 BEcorroborated

Remaining: 19.5 md (BE 10 + FE 4 + QA 4.5 — Tasks 1.1, 1.2, 2.3, 2.6-2.10 not started).