Delivery Timeline

MilestoneEffort (BE/FE/QA…)ConfidenceProgressTarget DateStatus
PRD finalized0/0TBDPending
RFC kickoff0/0TBDPending
Development start0/0TBDPlanned
Release0/0TBDPlanned

Dependencies & gates

  • 🟡 Mekari Billing / ModPanel — exact Lite component code strings (lite_user_initial / lite_user_additional); placeholder today (Open Q2). Blocks the Lite entitlement read (Task 2.3).
  • 🟡 Platformlite_seats_enabled CID-flag delivery mechanism + event schema (company_features row vs Kafka on bifrost.company.settings.events.v1) (Open Q3). Blocks auto-provisioning (Task 2.7).
  • 🟡 Design — Lite-config Figma frame (permission counter + inbox grey-out). Blocks FE Task 1.2.
  • (internal) inbox-related permission_key blocklist needs definition (Open Q1) — Bifrost eng.

BE chunks 1–8 + the FE flag/dropdown chunk are execution-ready; the FE counter/grey-out chunk is blocked on Figma.