Summary
First measurable progress: 0% → 33% (4.0 / 12 md). Phase-1 Task 1.1 (hub-core billing flag layer + deduction guard) is Done and code-corroborated. Three more Phase-1 tasks are Done on the board but code evidence is PARTIAL (repos without sibling checkouts).
Progress
progress_done_days = 4.0 of effort_total_days = 12 → 33%.
| Done task | Jira | Effort | Code evidence |
|---|---|---|---|
| Task 1.1 — hub-core billing flag + deduction guard + fail-safe | BIF-8807 | 3.0 BE + 1.0 QA = 4.0 | corroborated ✓ |
| Task 1.2 — qontak-billing modpanel MCC export filter | BIF-8808 | 1.0 BE | PARTIAL — qontak-billing unchecked (no sibling checkout) |
| Task 1.3 — report-worker client quota export filter | BIF-8809 | 1.0 BE | PARTIAL — report-worker unchecked |
| Task 1.4 — moderator-be service margin | BIF-8810 | 2.0 | Won't Fix (descoped) — 0 md |
| RFC document | BIF-8762 | — | code-free (Documents ticket) |
Tasks 1.2/1.3 Done on board but excluded from the sum until code is corroborated (could add 2.0 md → 50% if confirmed). Task 1.4 Won't Fix. Remaining: 8.0 md (Phase-1 Task 1.5 FE + Phase-2 Tasks 2.1/2.2, all gated on pricing decision / hub_core access).