0002 — WABA-S0x Story clones under BIF-8910, with per-story done/not-done reconciliation
Delivery / Program Management — decision record (ADR-style).
Context
Decision record 0001-jira-done-plan-open-conflict.md established that Epic BIF-6428 (closed,
26Q1 phase) holds the 7 original Stories (BIF-6919–BIF-6925, one per WABA-S01–WABA-S07),
all still Waiting Confirmation, and that the live 26Q3 Epic BIF-8910 is where the remaining
work belongs. A jira-alignment-check pass (2026-07-22) found only 1 of the 7 WABA-Sxx Stories
(WABA-S04 → BIF-8963) existed under BIF-8910 — the other 6 were flagged as a per-user-story
alignment gap (D4) and deliberately held pending a DRI/human call on how to resolve it, since simply
creating 6 fresh, empty Stories would have discarded the real (and uneven) completion evidence
already recorded against the legacy Stories' child Tasks.
A direct read of BIF-6428's Task tree (grouped by Work item split links to each of the 7 legacy
Stories) shows the actual per-story state is not uniform:
| Story | Legacy ref | Dev evidence |
|---|---|---|
| WABA-S01 — WABI Monthly Reset & Priority | BIF-6919 | All 3 child tasks Won't Fix — no shared-pool WABI reset work tracked as Done |
| WABA-S02 — WAB-Additional Purchase & Carry-Over | BIF-6920 | BE carry-over Done (BIF-7200); 3 QA tasks Won't Fix |
| WABA-S03 — Postpaid Limit Configuration & Blocking | BIF-6921 | BE reset/aggregation Done (BIF-7204); 2 QA tasks Won't Fix |
| WABA-S04 — Multi-Bucket Balance Deduction Hierarchy | BIF-6922 | Column/lookup/package-logic Done; backfill + FE aggregated display Won't Fix; blocking unique-index gap still open — already re-tracked as fresh BIF-8963/BIF-8971 |
| WABA-S05 — WABA ID Column in Usage Reports | BIF-6923 | 7 tasks + 2 bugfixes Done, code-corroborated; only broad API/E2E QA tasks Won't Fix; MCC filter dropdown (AC-3/4) untracked |
| WABA-S06 — Company-Level Low Balance Notifications | BIF-6924 | BE threshold logic Done (BIF-7221); QA Won't Fix; balance_below_zero event + LowBalanceBanner not built |
| WABA-S07 — Shared Balance Tooltip | BIF-6925 | BIF-7223 marked Done but falsely — no SharedBalanceTooltip component exists in hub-chat (per 0001) |
Decision
We will create one new Jira Story per missing WABA-Sxx under BIF-8910 (WABA-S01, S02, S03,
S05, S06, S07 — S04 already exists as BIF-8963), each carrying:
- The PRD user-story statement and a pointer to its full ACs in
bifrost/one-cid-multiple-waba/prds/prd-one-cid-multiple-waba-phase-1.md§8. - An explicit Status reconciliation section stating what is done, partially done, or not done, with the specific Jira task keys and code evidence backing that call (from the table above).
- A
Clonerslink (clones/is cloned by) to the corresponding legacy Story under BIF-6428, so the new Story is not a blank restart — it carries a real, navigable reference to the original work and its task-level history.
Created:
| WABA-Sxx | New Story (BIF-8910) | Clones (legacy, BIF-6428) | Reconciled state |
|---|---|---|---|
| S01 | BIF-9051 | BIF-6919 | Not done |
| S02 | BIF-9052 | BIF-6920 | Partially done — dev done, untested |
| S03 | BIF-9053 | BIF-6921 | Partially done — dev done, untested |
| S04 | BIF-8963 (pre-existing) | BIF-6922 | Not done — core mechanism gap, tracked via BIF-8971 |
| S05 | BIF-9054 | BIF-6923 | Done, with one open gap (filter dropdown) |
| S06 | BIF-9055 | BIF-6924 | Partially done — below-zero event + banner not built |
| S07 | BIF-9056 | BIF-6925 | Not done — Jira/code mismatch on BIF-7223 |
Rejected alternative: re-parenting/renaming the legacy Stories directly onto BIF-8910 and
retiring BIF-6428 (option (b) considered during the original jira-alignment-check remediation).
This was not chosen because it would rewrite history on issues that already carry real, dated task
completions from the 26Q1 phase — cloning preserves that trail on BIF-6428 while giving BIF-8910 its
own clean, individually-tracked Stories for the 26Q3 remainder.
Consequences
- BIF-8910 now has all 7
WABA-SxxStories as direct children, closing the D4 alignment gap found by the 2026-07-22jira-alignment-checkpass. - Each new Story's description is the authoritative "what's left" statement for 26Q3 planning; the
legacy Stories under BIF-6428 remain as-is (
Waiting Confirmation) and are not edited — they stay the historical record, reachable from the new Stories via thecloneslink. - Sprint planning for this initiative should size and pull from the BIF-8910 Stories (BIF-9051–9056, BIF-8963), not the BIF-6428 legacy Stories.
- This does not close any