Qontak One Team Migration — Status 2026-07-20
Summary
The original 15.5-day slice retains its 12.5-day corroborated baseline, but new requirements reopen the initiative: General must contain all existing users and automatically receive future users, and Launchpad must trigger migration through private Chat/CRM endpoints. This added work is unsized and does not change the recorded 81% baseline into a new aggregate percentage.
Current evidence
- BIF-8864/BIF-8865/BIF-8866 are
In Deployment; BIF-8911 isTo Doon Izzul. - BIF-8795 remains
Waiting Confirmation, so Yoddi will validate General-team creation and membership on a newly created CID. - The Sprint 2 Jira pull contains no BIF-8642 items. The plan therefore records a coverage gap until the intended work is added to the board.
Next
- Grehasta implements the Launchpad trigger and confirms the Chat/CRM private endpoint contracts.
- Backfill every existing user idempotently and add every future user automatically.
- Estimate the added backend and QA work before recomputing total effort or progress.