Delivery Timeline

MilestoneEffort (BE/FE/QA…)ConfidenceProgressTarget DateStatus
PRD finalized0/0TBDPending
RFC + task-breakdownBE 2.5 · FE 2 · QA 2medium0/6.52026-07-01Done (BE agent-execution-ready; OQ-2 authorization sign-off pending)
Development startBE 2.5 · FE 2 · QA 2medium0/6.5TBDFE queue slot resolved (resequenced 2026-07-01 — runs after Qontak One Team, ahead of Centralized SSO Token); still blocked on OQ-2 + QA sequencing
Release6.5 totalmedium0/6.5TBDPlanned

Dependencies & gates

  • 🟡 OQ-2 (authorization) — infosec sign-off pending. PUT /billings/extras is today writable by any org admin/owner/supervisor/agent/member, not Ops-only as the PRD intends. Task 3 (BE key allowlist, 1.5 md incl. QA) is gated on this deciding Option B (gate the write); drops entirely if Option C (accept self-enable) is chosen. Owner: bifrost + infosec.
  • FE schedule slot — resolved 2026-07-01 (EM decision). Syafrizal M. is staffed and his queue was resequenced so this initiative's FE runs right after Qontak One Team, ahead of Centralized SSO Token (Self-Subs → Lite → Qontak One Team → Sales Invoice + Jurnal → Centralized SSO Token), instead of being stuck behind the 37-day SSO build. He remains at exactly 1.00 capacity — see ../../delivery/capacity.md. This pushes Centralized SSO Token's own FE start back ~3.5 md; see its delivery/timeline.md for that consequence.
  • 🟡 Frontend design pending — no Figma yet (RFC OQ-1); FE logic is buildable but final styling/placement awaits design, and execution needs a hub-chat consumer RFC.