Self-Subs — Status 2026-07-15
Delivery / Program Management — periodic status report.
Summary
Written up from sprint-resync pass 5 (2026-07-15) reconciling Bifrost Sprint 1 (21367)
against Jira. Health stays at-risk — the standing external-contract and FE-overcommitment
risks from 2026-06-30 are unchanged. First real BE progress this pass:
Task 2.1 (migration) is Done and code-corroborated, moving progress 0% → 3%
(0.5 / 17.5 md).
Highlights
- Task 2.1 (BIF-8790) done and merged to
hub-core, PR #8007 (sha9581b9ebe0) — 0.5 BE-days of the 17.5 md total. - A9's ~0.5 md FE preemption (recorded 2026-07-14) has since cleared; Self-Subs' FE work resumes per that entry's note.
Lowlights & blockers
- 🟡 Board-hygiene question — Tasks 2.3 and 2.4 read
Won't Fixbut carry real code traces. BIF-8803 (Task 2.3) is resolvedWon't Fixyet has an unmerged branch (hub-core:origin/BIF-8803-be-hub-core-task-2-3-selfsubscriptions-initiate-in); BIF-8804 (Task 2.4) is alsoWon't Fixwith no code trace at all. Both are excluded from this progress figure (Won't Fix≠ shipped) regardless. Worth confirming with Grehasta/TPM whether this work was redirected into a different ticket — two other issues (BIF-8791, BIF-8802) both claim "Task 2.2" under different repos, suggesting some task-id renumbering/duplication may have happened without updating the breakdown. - Standing risks unchanged from 2026-06-30: Mekari Billing / Mekari Pay / moderator-be external contracts still open; Syafrizal M. (FE) still over capacity.
Risk & dependency changes
- No change to scope/staffing.
Metrics
- Progress: 0.5 / 17.5 md (3%), up from 0%.
- Throughput this period: +0.5 md (Task 2.1).
- Forecast: p50/p85 still TBD — unchanged; see 2026-06-30 for the standing external-contract caveats.