Customer Event-Based Engine (CEBE) — Status 2026-06-26

Delivery / Program Management — periodic status report. health: carries the delivery-health status (backlog / on-track / at-risk / off-track / paused / completed); the doc-lifecycle status: stays in the linter enum (active).

Summary

Backlog: Q3 Phase 1 is defined at PRD level, but the joint Eng + Data RFC and named BE/Infra owners are still pending.

Highlights

  • Anchor and two Phase-1 child PRDs are drafted.
  • Phase 1 scope is explicit: core infrastructure, CDP customer-data events, and Marketing Broadcast/Ads events.

Lowlights & blockers

  • Joint Eng + Data RFC pending — owner: CDP Eng + Data.
  • BE/Infra implementors and effort man-days are still TBD; Data is owned by the external DATA Team (cross-squad).

Risk & dependency changes

  • Marketing SUPPORT track is gated on the Core Infrastructure TECH track reaching a stable schema and adapter in staging.

Metrics

Baseline reading (t0) — the dated sequence of these reports is the burnup trend.

  • Progress: 0 / TBD man-days (0%) — total pending DRI man-days.
  • Throughput this period: 0 (baseline).
  • Forecast: TBD (derived once effort is finalized).

Next period

  • Staff BE/Infra owners, start the joint RFC with the DATA Team (external squad) for Data, and confirm per-discipline man-days.