Customer Event-Based Engine (CEBE) — Status 2026-06-26
Delivery / Program Management — periodic status report.
health:carries the delivery-health status (backlog / on-track / at-risk / off-track / paused / completed); the doc-lifecyclestatus:stays in the linter enum (active).
Summary
Backlog: Q3 Phase 1 is defined at PRD level, but the joint Eng + Data RFC and named BE/Infra owners are still pending.
Highlights
- Anchor and two Phase-1 child PRDs are drafted.
- Phase 1 scope is explicit: core infrastructure, CDP customer-data events, and Marketing Broadcast/Ads events.
Lowlights & blockers
- Joint Eng + Data RFC pending — owner: CDP Eng + Data.
- BE/Infra implementors and effort man-days are still
TBD; Data is owned by the external DATA Team (cross-squad).
Risk & dependency changes
- Marketing SUPPORT track is gated on the Core Infrastructure TECH track reaching a stable schema and adapter in staging.
Metrics
Baseline reading (t0) — the dated sequence of these reports is the burnup trend.
- Progress: 0 / TBD man-days (0%) — total pending DRI man-days.
- Throughput this period: 0 (baseline).
- Forecast: TBD (derived once effort is finalized).
Next period
- Staff BE/Infra owners, start the joint RFC with the DATA Team (external squad) for Data, and confirm per-discipline man-days.