Customer Segmentation — Status 2026-07-01
Delivery / Program Management — periodic status report.
health:carries the delivery-health status (backlog / on-track / at-risk / off-track / paused / completed); the doc-lifecyclestatus:stays in the linter enum (active).
Summary
Still at risk against the 2026-07-21 revenue commitment, but the effort picture materially
improved today: Julio Jeffer confirmed Backend at 4 man-days (0 — Basic Attributes build done in
Q2 — + 4 buffer bugfixing), and the FE task-breakdown (generated 2026-06-30) sizes FE 3 / QA 1.5.
8.5 of the initiative's man-days are now known; Data and Design remain unscoped, so
effort_total_days and the forecast stay TBD.
Highlights
- BE Jeffer-confirmed (2026-07-01): 4 man-days — the Basic Attributes backend build is done
(shipped in Q2), leaving only buffer bugfixing in Q3 scope. This also resolves the previously
flagged shared-BE-owner sequencing risk against Legacy Migration Activity Logs (P5) — see that
initiative's
2026-07-01status update. - FE task-breakdown (
customer-segmentation-fe.task-breakdown.md, 2026-06-30) sizes Tasks 2.1-2.3 at FE 3 / QA 1.5. - Reconciled into README
effort_*frontmatter and mirrored tocdp/delivery/roadmap.mdandcapacity.md(Azani FE load 0.19→0.25; Hendry QA load 0.34→0.37; Julio Jeffer BE load →0.40).
Lowlights & blockers
- Data and Design man-days remain unscoped — owner: DRI; ask: confirm
effort_data_days/effort_design_dayssoeffort_total_daysand a dated forecast can be computed. - The external Basic Attributes backend RFC noted in the prior status is still not mirrored into
this repo's
rfcs/folder (only the internal BE task-breakdown target is); Use-Case Activities RFC is still pending.
Risk & dependency changes
- Resolved: the Julio Jeffer shared-BE-owner sequencing risk vs. P5 (Legacy Migration Activity
Logs) flagged earlier today — both his revenue-dated tracks are now Jeffer-confirmed (this
initiative 4 days, P5 17 days), 21 days combined against 52 effective (
load 0.40).
Metrics
Baseline reading (t0) — the dated sequence of these reports is the burnup trend.
- Progress: 0 / 8.5 known man-days (0%) — Data/Design still pending, so the true total effort denominator is not yet final.
- Throughput this period: 0 (baseline).
- Forecast: TBD (derived once Data/Design are sized).
Next period
- DRI confirms Data/Design man-days so
effort_total_daysand a dated forecast can be computed. - Mirror the external Basic Attributes BE RFC into this repo's
rfcs/, or confirm it is superseded by the internal task-breakdown source.