Customer Segmentation — Status 2026-07-10

Delivery / Program Management — periodic status report. health: carries the delivery-health status (backlog / on-track / at-risk / off-track / paused / completed); the doc-lifecycle status: stays in the linter enum (active).

Summary

First real progress against the 8.5 known man-days baselined 2026-07-01: Hendry's QA test-case slice (TF-3490, Lane C) is Done in sprint 21382, landing 1.5 of the 8.5 known days (18%). The three FE integration-test tasks (TF-3399/3400/3401, Azani) are actively in flight but not yet Done, so they are not credited yet. Still at risk against the 2026-07-21 revenue commitment — one QA slice landing does not resolve the remaining FE runway.

Highlights

  • QA test-case writing complete (Hendry, TF-3490, Done). 1.5 confirmed QA days landed.
  • FE integration-test work is moving: TF-3399 (SegmentStore tests) is In Testing, TF-3400 (SegmentListPage tests) and TF-3401 (reachability fields) are In Progress — none Done yet.

Lowlights & blockers

  • Data and Design man-days remain unscoped — unchanged from 2026-07-01.
  • Only ~11 days remain to the 2026-07-21 commitment; the 3 FE days (TF-3399/3400/3401) need to land Done this week to keep pace, given TF-3401 depends on TF-3400's spec file.

Risk & dependency changes

  • No change from 2026-07-01 — the shared-BE-owner risk vs. Legacy Migration Activity Logs remains resolved on capacity.

Metrics

  • Progress: 1.5 / 8.5 known man-days (18%) — up from 0% on 2026-07-01.
  • Throughput this period: 1.5 days (QA slice).
  • Forecast: still TBD (Data/Design unscoped).

Next period

  • Land TF-3399/3400/3401 (FE) Done to keep pace against 2026-07-21.
  • DRI still needs to confirm Data/Design man-days so effort_total_days and a dated forecast can be computed.