Customer Segmentation — Status 2026-07-21 (commitment day)
Delivery / Program Management — periodic status report (Sprint 1 close; the 2026-07-21 revenue commitment date is today).
Summary
Commitment-day state: not shipped, but at the door. TF-3401 (Task 2.3, reachability fields — the last priced FE task, 0.5d) cleared its OQ-FE-2 block and sits at READY TO DEPLOY; it is not Done, so the burnup stays 4.0 / 8.5 known man-days (47%). 9 of 10 sprint issues done. Health stays at-risk until the deploy lands and the DRI records the commitment outcome (shipped-late vs degraded-ship).
Highlights
- TF-3401 unblocked (was Blocked on OQ-FE-2 at 2026-07-17) and Ready to Deploy.
- TF-3537 (chat data to S2S segment customers) Done — the 6th datamart BE item under this Epic.
Lowlights & blockers
- The 07-21 commitment is not Done on the board today — deploy pending; DRI to record the outcome in the next dated status.
- F-8 (escalated, 4th recheck, grew): now 6 done unpriced datamart BE items (TF-3507/3508/3511/3518/3519 + TF-3537) — silent P1 scope growth, retro-cost still pending.
Metrics
- Progress: 4.0 / 8.5 known man-days (47%) — unchanged from 2026-07-17.
- Throughput this period: 0 credited days (TF-3401 not Done; datamart items unpriced).
Next period
- Deploy TF-3401 and record the commitment outcome.
- DRI: retro-cost or declare out-of-band the 6 datamart items (F-8).