Two PRDs under one anchor: Basic Attributes (foundation, in progress under Jira epic TF-2544) and Use-Case Activities (cross-module associations, draft).
| Milestone | Track | Effort | Confidence | Progress | Target Date | Status |
|---|
| Anchor + 2 child PRDs documented | both | — | — | 0/0 | 2026-06-26 | Done |
| Jira epic TF-2544 active | basic-attributes | — | High | Jira active | 2026-06-27 | In Progress |
| Basic Attributes — backend RFC/design located | basic-attributes | — | Medium | Jira active | 2026-05-19 | External RFC exists |
| Basic Attributes — build | basic-attributes | TBD | — | Jira active / TBD days | 2026-Q3 | In Progress |
| Use-Case Activities — RFC | use-case | — | — | 0/0 | TBD | Pending |
| Use-Case Activities — build | use-case | — | — | 0/0 | 2026-Q3 | Planned |
| Internal Alpha → Open Beta → GA | both | — | — | 0/0 | 2026-Q3 | Planned |
Jira Evidence
- Jira epic TF-2544 is
In Progress.
- Child work spans done design/foundation, active membership/recalc, and remaining FE/QA tasks; dated key-level evidence lives in the dated status files.
- Rovo search found the external Confluence RFC
DRAFT RFC — Customer Segmentation based on Basic Attributes (Backend) submitted 2026-05-19 and related to TF-2544; it is not mirrored in this repo's rfcs/ folder.
- Jira proves Basic Attributes work is in progress, but delivery burnup still cannot be derived until
effort_<discipline>_days and effort_total_days are confirmed.
Staffing
| Discipline | Implementor |
|---|
| Backend | Julio Jeffer |
| Frontend | Azani |
| Data | DATA Team (external squad) |
| QA | Hendry (primary), Izzul (backup) |