Export Customer Data with Layout — Status 2026-07-01
Delivery / Program Management — periodic status report.
health:carries the delivery-health status (backlog / on-track / at-risk / off-track / paused / completed); the doc-lifecyclestatus:stays in the linter enum (active).
Summary
First dated status report for this initiative (previously unfiled). No commitment date and no build has started yet (Backlog), but the RFC was synced to PRD v2.6 and re-reviewed (R2, 2026-06-30) since the last delivery-layer refresh, growing effort +5.5 days (27 → 32.5) — mostly FE.
Highlights
- RFC review R2 (2026-06-30): 8.5/10,
Agentic-Ready, verdictPROCEEDfor the core pipeline (EXP-S01–S07, S09); EXP-S08 stays specified-but-not-buildable (OQ-17, Should-Have only). - Effort refreshed: BE 15 (Ghozi, unchanged) / FE 7.5 (was 3.5) / Mobile 5 (Alfi, unchanged) / QA 5 (was 3.5) = 32.5 total (was 27), driven by v2.6 chunks 18–21 (timezone formatting, first_10k shortcut, right-panel completion).
Lowlights & blockers
- Unchanged dependency set: Billing/IAG + Chat/Omnichannel (🔴, OQ-17, non-core only), One Notification Team (🟡, OQ-10), Alibaba OSS / CDP Infra (🟡, OQ-4), optional Mobile tap-through (🟡, OQ-12, non-blocking).
- New from R2: timezone value format ambiguity (OQ-20, major) and Source enum gap (OQ-21, minor) need confirmation before chunks 18/21.
Risk & dependency changes
- Forecast p85 pushed ~1 week (2026-09-11 → 2026-09-19, timeline-mapper 2026-07-01) as the +4 FE days land behind Jovi's existing P1 queue. No commitment date on this initiative, so the slip does not yet threaten a hard deadline — but it compresses buffer against the 2026-09-30 quarter end and should be re-confirmed once Jovi's Create-Ticket-web Task 1 (1.5 FE days) is also slotted.
Metrics
Baseline reading (t0) — the dated sequence of these reports is the burnup trend.
- Progress: 0 / 32.5 man-days (0%).
- Throughput this period: 0 (baseline).
- Forecast: p50 2026-09-02, p85 2026-09-19 (derived; core pipeline only).
Next period
- Confirm whether the v2.6 scope additions (chunks 18–21) ship in this same release or split out.
- Resolve OQ-20 (timezone format) and OQ-21 (source enum) before chunks 18/21 start.