Export Customer Data with Layout — Status 2026-07-21
Delivery / Program Management — periodic status report (Sprint 1 close).
Summary
Ghozi's whole BE chain cleared the testing lane: Tasks 2.1–2.5 (TF-3284–3288 — foundation, serializers, email/notification client, export consumer, handler/routes) are Done and code-corroborated — 11.5 of 32.5 man-days (35%), up from 0%. Board: 14 of 18 sprint issues done, 4 WIP (3 Ready to Test, 1 Blocked). Health on-track; forecast p85 2026-09-19 unchanged.
Highlights
- BE Tasks 2.1–2.5 (11.5d) merged to
contact-servicedefault — the initiative's first credited progress. - TF-3375 (Mobile tap-through routing) Done — maps to the roadmap's 5 Mobile days but has no breakdown row; flagged for retro-cost, uncredited.
Lowlights & blockers
- F-19: TF-3429/TF-3430 (CHAT report-page FE) are board-Done with code only on unmerged branches — 0-credited until merged. Jovi/TPM: merge or revert board status.
- F-21 (scope-watch): 5 done issues sit outside the 26-day breakdown (TF-3525 "Task 1.5", net-new APIs TF-3538/3542/3547, TF-3512 drawer expose) — scope has grown without retro-costing; DRI call needed (same shape as Segmentation's F-8).
- TF-3531 (CHAT history API integration) Blocked; TF-3283/3289/3378 Ready to Test.
Metrics
- Progress: 11.5 / 32.5 man-days (35%) — first credit; was 0% since 2026-06-24.
- Throughput this period: 11.5 BE days (TF-3284–3288).
- Evidence: board Done in sprint 21382 + merged code in
contact-service(engine corroboration, 11/14 done issues; gaps are F-19 ×2 + the code-free QA doc TF-3494).
Next period
- Merge TF-3429/3430 (F-19), then credit their FE days.
- DRI: retro-cost the F-21 off-breakdown set into the breakdown/README effort.
- Clear the Ready-to-Test lane (TF-3283/3289/3378) and unblock TF-3531.