Legacy Migration CRM Activity Logs → CDP — Status 2026-07-17

Delivery / Program Management — periodic status report. health: carries the delivery-health status (backlog / on-track / at-risk / off-track / paused / completed); the doc-lifecycle status: stays in the linter enum (active).

Summary

Task 2 (contact finder FindOneByCrmDataID, CALM-S01/S03 — TF-3465) is Done and code-corroborated: merged contact-service PR #861 (3a6be927). 2.0 of 24.5 known CDP-side man-days (8%, up from 4% on 2026-07-13). Tasks 3–9 still have no board items (sprint finding F-1), and the Stage-0 CRM DSN/query-plan gate still blocks any run — health stays at-risk.

Highlights

  • TF-3465 Done (Task 2, Julio Jeffer) — merged: contact-service PR #861 (3a6be927). 1.0 BE day.
  • Hendry's QA test-case slice for this initiative (TF-3493) is In Progress.

Lowlights & blockers

  • Tasks 3–9 (TF-3466–3472) remain absent from sprint 21382 (F-1, 8th consecutive pass) — 16 of the 17 BE days have no board presence; the burnup can't move past 8% until they are filed and worked.
  • Stage-0 gates (CRM read-only DSN + query-plan check) unchanged — build-ahead only.

Metrics

  • Progress: 2.0 / 24.5 known CDP-side man-days (8%) — up from 4% on 2026-07-13.
  • Throughput this period: 1.0 BE day (TF-3465).
  • Evidence: board Done in sprint 21382 + merged code (contact-service PR #861).

Next period

  • TPM: file Tasks 3–9 into the sprint/board (F-1) — Task 3 (schema transformer, 3 BE days) is the next critical-path chunk.