Legacy Migration: CRM Activity Logs → CDP — Status 2026-07-21
Delivery / Program Management — periodic status report (Sprint 1 close).
Summary
The board is green; the initiative is not. All 4 TF-3182 sprint issues read Done, but only
Tasks 1–2 (2.0 of 17 BE days) are real credited progress — Tasks 3–9 (TF-3466–3472, 15 BE
days) were never added to the sprint (finding F-1, open since pass 1). Recorded as
F-23 blocked-done-conflict: health stays at-risk, not flipped from board optics.
Progress unchanged at 2.0 / 24.5 known man-days (8%).
Lowlights & blockers
- F-23 / F-1: the 8-week 2026-08-04 commitment has 15 of 17 BE days with zero board presence — Sprint 2 planning must file TF-3466–3472 into the sprint deliberately.
- TF-3459 duplicate closed Won't Fix (F-3 resolved — board hygiene done).
- Stage-0 gates (CRM read-only DSN, query-plan check) still pending — run remains gated.
Metrics
- Progress: 2.0 / 24.5 known man-days (8%) — unchanged from 2026-07-17.
- Board count-note: 4/4 sprint issues done (2 code-corroborated; TF-3493 QA doc code-free, TF-3459 Won't Fix uncredited).
Next period
- File Tasks 3–9 into Sprint 2 (closes F-1's CALM half; F-23 resolves with it).
- Chase Gate A/B (DSN access + query plan) ahead of the 2026-08-04 date — forecast pressure is real: 15 BE days remain with 2 weeks to the commitment.