Mention User in CDP Notes — Status 2026-06-30

Delivery / Program Management — periodic status report. health: carries the delivery-health status (backlog / on-track / at-risk / off-track / paused / completed); the doc-lifecycle status: stays in the linter enum (active).

Summary

At risk: the 2026-07-14 revenue commitment is not achievable at full scope. The initiative is the squad's P1 and fully estimated (30.5 md), but it starts the quarter at 0% and the mandatory BE-first dark deploy (10 BE-days ≈ 2 weeks) plus mobile/FE/QA and two external gates push the realistic finish to early–mid August — a ~3–4 week miss against the date.

Highlights

  • RFC R3 (2026-06-22) is Agentic-Ready, verdict PROCEED; the notification-service contract is verified and 9/10 chunks are unblocked for build.
  • Effort confirmed: BE 10 (Berlianto), FE 6 (Jovi), Mobile 10 (Alfi), QA 4.5 (Hendry) = 30.5 md.

Lowlights & blockers

  • Scope-vs-date conflict (priority/deadline inconsistency). The roadmap names this P1 with first claim on capacity, yet its commitment_date: 2026-07-14 is the earliest and least achievable of the squad's five revenue dates. Honouring "P1 first" still misses 07-14 — derived forecast_p50: 2026-08-05 / p85: 2026-08-14. Leadership decision required: cut to a shippable slice (e.g. BE + mobile dark-deploy, defer the web composer that waits on Figma) or move the date.
  • Design (🔴, OQ-14) — owner: Design System; web Figma frames for the typeahead picker + chip gate the web composer (§4.D chunk 7); no committed date.
  • Infosec (🟡) — bluemonday allow-list + lock-screen PII egress ack required before GA.

Risk & dependency changes

  • New deadline-vs-scope risk recorded from the 2026-06-30 timeline-mapper run: full-scope finish forecast lands ~3 weeks past the 2026-07-14 commitment. Dependency gates tracked in timeline.md ## Dependencies & gates; forecast mirrored to README forecast_*.
  • Shared-owner note: Berlianto (BE) is sequential into the P4 CRM-Notes migration — that initiative cannot start its BE until this one's BE completes.

Metrics

Baseline reading (t0) — the dated sequence of these reports is the burnup trend.

  • Progress: 0 / 30.5 man-days (0%).
  • Throughput this period: 0 (baseline).
  • Forecast: p50 2026-08-05 / p85 2026-08-14 (judgment) — misses commitment 2026-07-14.

Next period

  • Leadership decision on scope-cut vs date-move; secure a Figma OQ-14 date from Design and the Infosec ack; begin BE dark-deploy chunks 1–5 to bank progress against the forecast.