Mention User in CDP Notes — Status 2026-06-30
Delivery / Program Management — periodic status report.
health:carries the delivery-health status (backlog / on-track / at-risk / off-track / paused / completed); the doc-lifecyclestatus:stays in the linter enum (active).
Summary
At risk: the 2026-07-14 revenue commitment is not achievable at full scope. The initiative is the squad's P1 and fully estimated (30.5 md), but it starts the quarter at 0% and the mandatory BE-first dark deploy (10 BE-days ≈ 2 weeks) plus mobile/FE/QA and two external gates push the realistic finish to early–mid August — a ~3–4 week miss against the date.
Highlights
- RFC R3 (2026-06-22) is
Agentic-Ready, verdictPROCEED; the notification-service contract is verified and 9/10 chunks are unblocked for build. - Effort confirmed: BE 10 (Berlianto), FE 6 (Jovi), Mobile 10 (Alfi), QA 4.5 (Hendry) = 30.5 md.
Lowlights & blockers
- Scope-vs-date conflict (priority/deadline inconsistency). The roadmap names this P1 with
first claim on capacity, yet its
commitment_date: 2026-07-14is the earliest and least achievable of the squad's five revenue dates. Honouring "P1 first" still misses 07-14 — derivedforecast_p50: 2026-08-05/p85: 2026-08-14. Leadership decision required: cut to a shippable slice (e.g. BE + mobile dark-deploy, defer the web composer that waits on Figma) or move the date. - Design (🔴, OQ-14) — owner: Design System; web Figma frames for the typeahead picker + chip gate the web composer (§4.D chunk 7); no committed date.
- Infosec (🟡) — bluemonday allow-list + lock-screen PII egress ack required before GA.
Risk & dependency changes
- New deadline-vs-scope risk recorded from the 2026-06-30 timeline-mapper run: full-scope finish
forecast lands ~3 weeks past the 2026-07-14 commitment. Dependency gates tracked in
timeline.md## Dependencies & gates; forecast mirrored to READMEforecast_*. - Shared-owner note: Berlianto (BE) is sequential into the P4 CRM-Notes migration — that initiative cannot start its BE until this one's BE completes.
Metrics
Baseline reading (t0) — the dated sequence of these reports is the burnup trend.
- Progress: 0 / 30.5 man-days (0%).
- Throughput this period: 0 (baseline).
- Forecast: p50 2026-08-05 / p85 2026-08-14 (judgment) — misses commitment 2026-07-14.
Next period
- Leadership decision on scope-cut vs date-move; secure a Figma OQ-14 date from Design and the Infosec ack; begin BE dark-deploy chunks 1–5 to bank progress against the forecast.