Mention User in CDP Notes — Status 2026-07-10
Delivery / Program Management — periodic status report.
health:carries the delivery-health status (backlog / on-track / at-risk / off-track / paused / completed); the doc-lifecyclestatus:stays in the linter enum (active).
Summary
First progress against the 34 md baselined 2026-07-01: Hendry's QA test-case slice (TF-3489) is Done, landing 4.5 of 34 known days (13%). Still at risk against the 2026-07-14 revenue commitment and the derived forecast (p50 2026-08-10 / p85 2026-08-19) is unchanged — a QA slice landing does not move BE/FE critical-path dates.
Highlights
- QA test-case writing complete (Hendry, TF-3489, Done). 4.5 confirmed QA days landed.
- Berlianto's BE tasks (TF-3325–3330, note model → mention parser → sanitizer → active-user validation → wire-in → async notify job) remain To Do in the sprint — none started yet.
- Jovi's FE wiring tasks (TF-3331 composer/renderer, TF-3382 preview-card user detail) are In Progress but not Done.
Lowlights & blockers
- No BE work has started yet despite being the critical path for the 08-14 date — flag for Berlianto/DRI: BE Tasks 2.1–2.6 have not moved off To Do.
- Design (OQ-14) and Infosec gates unchanged from 2026-07-01.
Risk & dependency changes
- No change from 2026-07-01 — forecast and downstream P5 (Legacy Migration: CRM Notes) impact unchanged.
Metrics
- Progress: 4.5 / 34 man-days (13%) — up from 0% on 2026-07-01.
- Throughput this period: 4.5 days (QA slice).
- Forecast: p50 2026-08-10 / p85 2026-08-19 (judgment, unchanged) — still misses commitment 2026-07-14 by ~4 weeks.
Next period
- Escalate: BE Tasks 2.1–2.6 (Berlianto) have not started — this is the critical path to 08-14/ the derived forecast; confirm start date.
- Same leadership decision as 2026-07-01: scope-cut vs date-move.