Mention User in CDP Notes — Status 2026-07-21
Delivery / Program Management — periodic status report (Sprint 1 close).
Summary
The full BE chain is now shipped: Tasks 2.4 (TF-3328, active-user validation, 0.5d), 2.5 (TF-3329, wire into create/update, 3.0d) and 2.6 (TF-3330, async notify job, 3.0d) landed Done and code-corroborated — 17.5 of 34 man-days (51%), up from 32% on 2026-07-17. On the board 16 of 17 sprint issues are done; only TF-3509 (deleted-user fallback display, FE) is still Ready to Test. Health on-track for the 2026-08-14 commitment.
Highlights
- BE Tasks 2.1–2.6 all Done and merged (
contact-service, enginecode:evidencecorroborated). - FE integration (Tasks 2.7/2.8) and 7 Mobile items done (Mobile uncredited — F-7).
Lowlights & blockers
- F-17 (escalated): FE Phase-1 tasks 1.1–1.4 (~7 FE days) have no board issues while the
Phase-2 work built on them is Done — the 51% burnup understates real progress (≈72% if
Phase 1 were credited). TPM/Jovi to backfill via
sprint-jira-sync. - F-7 (escalated, 4th recheck): 7 done Mobile items remain unpriced/uncredited — DRI/PM retro-cost decision still pending.
Metrics
- Progress: 17.5 / 34 man-days (51%) — up from 32% on 2026-07-17.
- Throughput this period: 6.5 BE days (TF-3328, TF-3329, TF-3330).
- Evidence: board Done in sprint 21382 + merged code in
contact-service(engine corroboration, 13/16 done issues; the 3 uncorroborated are code-free QA/Mobile-verify tasks).
Next period
- Backfill FE Phase-1 board items (F-17), then recompute burnup.
- Resolve the Mobile retro-cost call (F-7).
- Land TF-3509, then QA gate toward the 2026-08-14 commitment.