Team Owner Field & Team Permission — Status 2026-06-30
Delivery / Program Management — periodic status report.
health:carries the delivery-health status (backlog / on-track / at-risk / off-track / paused / completed); the doc-lifecyclestatus:stays in the linter enum (active).
Summary
At risk against the 2026-08-18 revenue commitment. The in-repo BE/FE/Mobile chunks are implementation-ready against the pinned §2.4 contract, but flag-ON GA is gated on Launchpad delivering work that is not yet committed — so the deadline is exposed to a dependency this squad does not own.
Highlights
- RFC R2 (2026-06-18) is
Agentic-Ready, verdictPROCEED; all in-repo chunks are executable. - Effort partially confirmed: BE (Ghozi, 10d), FE (Azani, 10d), Mobile (Alfi, 10d) = 30d so far; Design/QA man-days still pending.
Lowlights & blockers
- Launchpad dependency (🔴, GA blocker) — owner: Launchpad; ask: ship the teams-for-user
(+descendants) endpoint to the §2.4 contract and the
teamradio in permission settings UI (CHG-001) before flag-ON GA. Radio ownership is ambiguous (Launchpad vs Admin Portal) and needs confirming. - Mobile module (🔴) — owner: Mobile Squad; ask: render the Team Owner field + per-note permission flags.
- Legacy→Launchpad team-name crosswalk (🔴) — owner: Launchpad + CDP; needs building for the migration step.
Risk & dependency changes
- New deadline-vs-dependency risk recorded: the 2026-08-18 commitment is gated on uncommitted
Launchpad deliverables (dependency-check, 2026-06-30). Tracked on the roadmap
## External & cross-squad dependenciesand this initiative'stimeline.md## Dependencies & gates. Health moved Backlog → At Risk to reflect the exposure.
Metrics
Baseline reading (t0) — the dated sequence of these reports is the burnup trend.
- Progress: 0 / 30+ man-days (0%) in repo burnup; total pending Design/QA man-days.
- Throughput this period: 0 (baseline).
- Forecast: TBD (derived once Design/QA man-days and the Launchpad delivery date are confirmed).
Next period
- Secure a Launchpad commitment + date for the teams-for-user endpoint and Team Only radio; confirm radio ownership; confirm Design/QA man-days so the TPM can derive a GA forecast against the 2026-08-18 date.