Team Owner Field & Team Permission — Status 2026-07-21

Delivery / Program Management — periodic status report (Sprint 1 close). Progress is count-based until the breakdown carries effort estimates.

Summary

The entire BE surface shipped this sprint: all 12 TEAM-S backend stories (TF-3448–3458, TF-3488 — field, LP integration, all TEAM-ONLY permission enforcements, auto-sync, flag guard) are Done, 12/13 done issues code-corroborated. FE Tasks 1–5 (TF-3312–3316) all sit at READY TO DEPLOY. Board count-note: 13 of 18 sprint issues done. Man-day burnup stays 0% — the newly authored task-breakdown (closing F-5) is a BE-only coverage mapping that deliberately carries no effort estimates, so done work cannot be priced yet.

Highlights

  • F-5 resolved: rfc-team-owner-field-and-team-permission.task-breakdown.md now exists (11 of 12 in-RFC BE chunks covered; gap: migration backfill job, chunk 11/CHG-004).
  • BE complete behind cdp_team_permission_enabled (default OFF), per plan.

Lowlights & blockers

  • F-5 residual: no effort estimates and no FE/Mobile mapping in the breakdown → progress stays count-based; DRI/Ghozi to add sizing so Q3 burnup can credit ~37.5 known days.
  • FE Tasks 1–5 parked at Ready to Deploy — deploy gate to clear early Sprint 2.
  • Flag-ON GA still gated on Launchpad (teams-for-user API, permission radio, crosswalk) and the Mobile Squad contract — unchanged from the sprint plan's blockers 1–2.

Metrics

  • Board count-note: 13/18 done (12 corroborated; TF-3491 QA doc code-free).
  • Man-days: 0 credited / TBD total (BE 10 + FE 10 + Mobile 10 + QA 7.5 known).

Next period

  • Deploy FE Tasks 1–5; size the breakdown (F-5 residual) so progress converts to man-days.