AI Agent Impact Report — Status 2026-07-16

Delivery / Program Management — periodic status report.

Summary

Sprint-resync pass 6 (2026-07-16) escalates a coverage gap on this initiative's Sprint 1 board presence. Progress/forecast are otherwise unchanged from the 2026-07-14 report (forecast_p50 2026-08-28 · forecast_p85 2026-09-18) — this entry adds the escalation, not a new estimate.

Risk & dependency changes

  • Escalating (sprint-resync pass 6, F-2, coverage-gap). BOT-4568 (P2) has carried exactly one board issue (BOT-4645, "QA Creation Testcases", non-dev) across all 6 resync passes since 2026-07-14, with zero BE/FE implementation Tasks filed. This directly bears on Sprint 1 outcome target 3 ("P2 AI Agent Impact Report has a buildable FE shell"), which this board state does not support. Six consecutive passes with no owner response is past the two-recheck escalation threshold in .claude/reference/sprint-resync.md §4.
  • Decision needed from Dimas Fauzi Hidayat (PM/TPM): either file the FE Phase-1-mocked and BE contract-scaffolding Tasks now via sprint-jira-sync (sprint mode), or explicitly descope Sprint 1's outcome target 3 to planning-only and record that in the sprint doc's ## Deviations section.
  • No change to the underlying bottleneck risk recorded 2026-07-14 (Baghiz Firdausa serialized across this initiative and AI Agent Testing, behind an unsized Google Calendar commitment) — still live, not restated in full here.

Metrics

  • Progress: 0 / 33.5 man-days (0%) — unchanged; no BE/FE work has been filed to make progress against.
  • Forecast: p50 2026-08-28 · p85 2026-09-18 (basis: judgment) — unchanged; the coverage gap itself is not yet a forecast input, since no work is filed to be late.

Next period

  • Resolve the F-2 decision above before the next resync pass — a 7th consecutive "still open" would itself be a process-health signal worth its own retro item.
  • Confirm Google Calendar's remaining Baghiz/Agus effort size (carried from 2026-07-14).
  • Push Data/BI for a committed datamart delivery date (carried from 2026-07-14).