AI Agent Testing — Status 2026-07-16

Delivery / Program Management — periodic status report.

Summary

Sprint-resync pass 6 (2026-07-16) escalates a code-evidence gap first flagged pass 2 (2026-07-15). Progress/forecast are otherwise unchanged from the 2026-07-14 report (p50 2026-10-04 · p85 2026-10-25, still off-track against the quarter) — this entry adds the escalation, not a new estimate.

Risk & dependency changes

  • Escalating (sprint-resync pass 6, F-14, code-evidence-gap). Four board issues under BOT-3351 — BOT-3949, BOT-4616, BOT-4617, BOT-4618 — are marked Won't Fix (done statusCategory) with no merged-code trace in chatbot/chatbot-fe across 5 consecutive resync passes (partial search — qontak-designer/hub not checked in any pass so far). progress_pct correctly excludes all four from the completed man-day sum (stays 0/37.5, 0%) per the "captures, never estimates" rule — this is not a math error, it is an unresolved status dispute.
  • Decision needed from the issues' assignee/DRI + Dimas Fauzi Hidayat (TPM): for each of the four, either confirm explicitly that the task is genuinely code-free (docs/config/no-op — state which) so it can be marked resolved next pass, or correct the board status if it was closed in error. Five checks with no resolution is past the two-recheck escalation threshold in .claude/reference/sprint-resync.md §4.
  • No change to the previously recorded quarter-fit conflict (Baghiz serialized behind Impact Report, Farras blocked until clearing P1) — still live, not restated in full here.

Metrics

  • Progress: 0 / 37.5 man-days (0%) — unchanged; 4 done / 5 in-progress of 12 sprint issues, but 0/4 done issues code-corroborated.
  • Forecast: p50 2026-10-04 · p85 2026-10-25 or later (basis: judgment, Low confidence — carried from 2026-07-14; the code-evidence gap does not itself move these dates, since the affected issues were already excluded from progress).

Next period

  • Resolve the F-14 decision above before the next resync pass.
  • Generate the task breakdown's remaining sequencing detail (carried from 2026-07-14).
  • Push the AI platform squad for a committed batch-capacity date (carried from 2026-07-14).