AI Agent Testing — Status 2026-07-26

Delivery / Program Management — periodic status report. Source: reconciliation pass 14.

Summary

F-14 remains escalated after eight passes. The board shows 10 done / 7 in-progress, with 6/10 code-corroborated; progress remains 0% until evidence joins the task breakdown.

Risk & dependency changes

  • F-14 code-evidence-gap — ⛔ escalated. BOT-3949, BOT-4616, BOT-4617, and BOT-4618 remain Won't Fix without merged-code evidence.
  • Decision owed — assignee/DRI + Dimas Fauzi Hidayat: confirm descope and reduce the 37.5-day baseline, or correct Jira.

Metrics

  • Progress: 0 / 37.5 man-days (0%).
  • Forecast: p50 2026-10-04 · p85 2026-10-25 (basis: judgment).

Next period

  • Land the F-14 descope decision and re-baseline effort.
  • Confirm the BOT-4654-to-breakdown join before crediting progress.