AI Agent Testing — Status 2026-07-27
Delivery / Program Management — periodic status report. Source: reconciliation pass 16 (Sprint 1 close).
Summary
First non-zero progress reading: 2.5 / 37.5 man-days (7%), derived from the breakdown, not
estimated. Board is 10 done / 7 in-progress. Read the number as a floor — 5 merged, corroborated
issues score 0 because they carry no breakdown task-id.
Metrics
- Progress: 2.5 / 37.5 man-days (7%), up from 0%.
- Basis: BOT-4615 → Task 2.4 "Delete and Re-run Test Case Contracts", breakdown effort
2.5d (BE 2 + QA 0.5), code-corroborated in
chatbotatefc0110a5(PR #2407) andf4a259058. - Forecast: p50 2026-10-04 · p85 2026-10-25 (basis: judgment) — unchanged; still overflows 2026-Q3.
Risk & dependency changes
- F-14
code-evidence-gap— ⛔ escalated (9th pass). BOT-3949, BOT-4616, BOT-4617, BOT-4618 remain Won't Fix with no merged code. Three of the four are the only breakdown-joinable done tasks besides Task 2.4, so this decision is what holds progress at 7%. Decision owed — assignee/DRI + Dimas Fauzi Hidayat: confirm the descope and re-baseline the 37.5-day total, or correct Jira. - F-52
status-progress— new, open. BOT-3942, BOT-3941, BOT-4188, BOT-4654 and BOT-4659 are all merged-code-corroborated (ca1584127/PR #2415,de035bc34/PR #2393,6ac332cbe/PR #2389,d871730d9/PR #2385,550b0e2a3/PR #2398) but carry noTask N.Nsummary token, so no breakdown effort can be attached without guessing. Ask the DRI to map each to its Phase-2 task or declare it out-of-breakdown work. This is the single largest lever on the real completion figure.
Next period
- Land the F-14 descope decision and re-baseline effort.
- Map the five F-52 issues to breakdown tasks so the 7% floor can rise to a true reading.