Autonomous AI Agent — Status 2026-07-14
Delivery / Program Management — periodic status report. Scope: Phase 2 (AI-Assisted Refinement / Refiner) only — Phase 1's GA gate is tracked separately in
2026-06-25.md.
Summary
initiative-timeline-mapper ran in squad mode (2026-07-14) across the four DRI-sized Chatbot
initiatives (this one, AI Agent Impact Report, AI Agent Testing, AI Agent Knowledge) to produce
week-level forecasts instead of the quarter-only target_quarter. For Phase 2 Refiner specifically:
on track for a p50 finish of ~2026-08-04, p85 ~2026-08-18 — comfortably inside 2026-Q3.
Highlights
- Task breakdown exists and is DRI-effort-confirmed: 24.5 md (FE 12 · BE 8 · QA 4.5), PM-confirmed per-person split 2026-07-13 (farras.herdicho BE, samudra.linggar FE).
- Sprint 1 (started 2026-07-13) has both owners actively on this as their top-priority (P1) item; chunks 1–8 (of 9) are buildable now against a stub, with no dependency on the still-unverified upstream.
Lowlights & blockers
- Samudra (FE, 12 md) is the longer pole vs. Farras (BE, 8 md) — dev-complete ~2026-08-02.
- External, no committed date: OQ-1a — Data/ML's
refine-skill-packupstream deployment/exposure is unverified. This blocks only the final real-upstream integration chunk (Task 2.7), not the bulk of the work, so it does not change the p50 but is the main risk behind the p85 buffer. - REV-6 (the breakdown's own named biggest risk): the RFC never tabulates the
updated_capability_pack→ flatAgentDetailConfigfield mapping; theuseRefineAgentdiffer (Task 1.1/1.3) carries real rework risk if the mapping turns out wrong. - Figma frames are still pending; the live prototype is the interim design source of truth.
Risk & dependency changes
- New this period: forecast dates now recorded (see frontmatter) — basis: total effort along the critical path (Farras BE → Samudra FE, serialized where shared) against Sprint 1's actual start date (2026-07-13), at 4 effective-days/person/week (5 days × 0.8 focus).
Metrics
- Progress: 0 / 24.5 man-days (0%) — work just started this sprint.
- Forecast: p50 2026-08-04 · p85 2026-08-18 (basis: judgment) — assumes Data/ML's upstream either lands in time for Task 2.7 or that chunk ships just after the p50 date without blocking the rest.
Next period
- Confirm Data/ML's
refine-skill-packexposure timeline (OQ-1a) — currently the only external unknown on this initiative's critical path. - Resolve REV-6's field-map ambiguity before Task 1.1/1.3 land, to avoid a differ rewrite.