Chatbot (BOT Squad) · Delivery Readiness

2026-Q3 Planning Readiness & Timeline Projection

Can BOT responsibly commit to its Q3 portfolio — and is there enough sized, staffed, unblocked work to say so?

Window: 2026-07-01 → 2026-09-30 (13 wks) · assessed 2026-07-09 · 12 portfolio initiatives (+1 off-roadmap) · source: chatbot/delivery/{roadmap,capacity}.md + initiative READMEs/timelines

Not ready to lock

Capacity itself is not the blocker — with a standard 52 effective-day/quarter assumption, no one is over (busiest: Baghiz Firdausa at 0.66×). The blockers are elsewhere: only 4 of 13 initiatives carry DRI-confirmed man-days (all task-breakdown-derived, none yet a formal sign-off); AI Agent Knowledge (P4) sits at an explicit RFC-review HOLD (4 cross-team sign-off blockers); five initiatives carry a 🔴 blocking external/cross-squad dependency with no committed resolution date from the owning team; and zero initiatives have a hard commitment_date — every date below is the soft target-quarter window only.

0
Commit-ready
2
Tentative
(sized, externally blocked)
2 + 11
Do not commit + park
0.66
Peak load — Baghiz Firdausa, across Autonomous Phase 2 FE + Impact Report FE + Testing FE; no one is over
4 / 13
Initiatives with DRI-confirmed effort man-days (Knowledge 13 · Testing 37.5 · Impact Report 33.5 · Autonomous Phase 2 24.5)
0
Hard commitment_dates in the portfolio — every date is the soft target-quarter window
5
🔴 blocking cross-squad / external dependencies, none with an owner-committed resolution date
108.5
Man-days sized so far, all four task-breakdown-derived (medium/medium-high confidence)

The commit decision — what each initiative needs

One row per initiative: why it can't be locked yet, the single action that closes the gap, and who owns that action. Ordered by the roadmap's ## Priority rank (P1→P14, unranked last). The effort & gate evidence is in §02; the timeline detail is in §03–§04.

InitiativeNowWhy it can't be committedWhat closes itOwner
Autonomous AI Agent — Phase 2 (Refiner)
P1 · no date · Phase 1 100% Jira done (80/80), production 2026-06-23 — sandbox-gated, not GA
Tentative Fully sized (FE 12 / BE 8 / QA 4.5 = 24.5md, medium confidence) and design-ready (Wulan's live prototype); RFC review PROCEED w/ notes (8.5). Per the task breakdown, chunks 1–8 (Tasks 1.1–2.6, ~22.5 of 24.5md) are executable today against the documented contract with a mocked/stub upstream — Farras, Samudra, Baghiz, Eko, and Tito can start now. Only Task 2.7's real-upstream + config-audit pass is 🔴 blocked, on Data/ML's refine-skill-pack endpoint (no committed date), and per-person split within BE/FE (2 owners each) is not itemized. Phase 1's own hard gate (unresolved autonomous/legacy staging runtime errors since 2026-06-03) blocks Pilot/GA separately and doesn't gate Refiner build. Start the BE/FE stub-and-mock slices now (already reflected in Sprint 1); get a date from Data/ML for refine-skill-pack to unblock Task 2.7 only; itemize the BE/FE split between the two named owners each. DRI (Dimas) + Data/ML
AI Agent Impact Report — Phase 1
P2 · no date
Do not commit Now fully sized (FE 15.5 / BE 10 / QA 8 = 33.5md, medium confidence, task-breakdown-derived) and fully staffed (Agus BE, Baghiz FE, Tito/Izzul QA — the squad's standard QA default) — but design is not started (Figma pending), and it depends on Data/BI's per-organization activity-log datamart (🔴 blocking, no date). Start the Figma design track; get a Data/BI datamart date. Staffing is no longer a gap. DRI (Dimas) + PM
AI Agent Testing — Phase 1 (Historical Validation)
P3 · no date
Tentative Fully sized (FE 13 / BE 16.5 / QA 8 = 37.5md, medium-high confidence — the best-evidenced initiative in the portfolio) and design-ready; RFC review PROCEED, best score in the portfolio (8.5, zero citation drift after 3 review cycles). Blocked solely on the AI platform squad's batch shadow-inference capacity (🔴, TPM/RPM limits) — no date given. Get a capacity-allocation date from the AI platform squad for the shared answer-evaluation engine; nothing else is missing. DRI (Dimas) + AI platform squad
AI Agent Knowledge — Phase 1 (Conversation History)
P4 · no date
Do not commit Sized (FE 1.5 / BE 8 / QA 3.5 = 13md) but its own RFC review verdict is an explicit HOLD (score 7.5) on 4 cross-team/sign-off blockers: webhook contract, masking SLA, Figma design frames, and division-scoping sign-off. Only BE chunks 1–6 + 2b are buildable today; 3 of 7 tasks are blocked. PRD is still `draft`. Clear the 4 HOLD blockers (REV-2/3/4/5) — two are external Data/AI gates due 2026-07-15, two need internal design/sign-off. DRI (Dimas) + Data/AI team
Unified Agent Scorecard — Phase 1 (Settings & Rubric)
P5 · no date
Park No effort recorded, no design (concept prompts only, not yet with a designer), no RFC review score yet. DSAI scoring-engine dependency is explicitly non-blocking for Phase 1 per its own PRD — the only bright spot. Get to a designer and size BE/FE/QA man-days; land an RFC review score. DRI (Dimas) + PM
Unified Agent Scorecard — Phase 2 (Auto-Scoring)
P6 · no date · depends on Phase 1
Park No effort, no design, no RFC. Depends on AI platform (DSAI)'s SkillPack evaluator output contract (🔴 blocking, no date) — and structurally can't start ahead of Phase 1. Sequence behind Phase 1; get a DSAI contract date before sizing. DRI (Dimas) + AI platform (DSAI)
Unified Agent Scorecard — Phase 3 (Analytics Report)
P7 · no date · depends on Phase 1/2
Park No effort recorded. Design partially exists (Metabase dashboard reused; host page/nav still needs design). Depends on Data/BI's unified Metabase dashboard + warehouse pipeline (🔴 blocking, no date). Get a Data/BI pipeline date; finish the host-page design once Phase 1/2 land. DRI (Dimas) + Data/BI (Analytics)
Mekari Action (AI Agent)
P8 · backlog-tier · target_quarter 2026-Q3
Park No RFC, no effort, no implementors recorded. `target_quarter` re-baselined to 2026-Q3 (2026-07-09) to match its 26Q3 backlog rank. Start an RFC; staff it and size man-days. DRI (Dimas) + TPM
Native Integration (AI Agent) — Midtrans Phase 1
P9 · backlog-tier · target_quarter 2026-Q3
Park Has an RFC with a review score (7, PROCEED w/ notes — one mandatory pre-seed fix, two open external confirmations) but no effort man-days and no implementors recorded. Its PRD also carries `jira_epic: BOT-4340` — the one PRD in the repo that would auto-populate per-AC Jira Stories if the (currently untriggered) automated sync ever ran; leave that pipeline untriggered per CLAUDE.md. Staff it and size man-days; resolve REV-1/REV-7's external confirmations. DRI (Dimas) + TPM
Qontak Action (AI Agent)
P10 · backlog-tier · target_quarter 2026-Q3
Park No RFC, no effort, no implementors. PRD header Epic (BOT-3476) drifted from the README's `jira_epic` (BOT-4341) — a wiring gap on top of the sizing gap. Fix the Epic drift in the PRD header; start an RFC and size the work. DRI (Dimas) + TPM
AI Agent Idle Action (Sequential Idle Follow-up)
P11 · backlog-tier
Park Best-reviewed unsized initiative in the portfolio — RFC review PROCEED, score 8.5 — but no effort man-days and no implementors recorded yet, purely a staffing/sizing gap, not a readiness gap. Assign implementors and size man-days — the RFC itself is execution-ready. DRI (Dimas) + TPM
AI Agent Monitoring (Supervisor Alerts)
P12 · backlog-tier
Park No RFC exists at all yet (PRD only) — the least-progressed initiative in the portfolio besides the off-roadmap MBA initiative. Start an RFC before any sizing/staffing conversation is possible. DRI (Dimas) + PM
Bot-vs-Human Traffic Split (A/B)
P13 · backlog-tier
Park RFC exists (draft) with a review file present but no score recorded yet; no effort, no implementors. Complete the RFC review and size BE/FE/QA man-days. DRI (Dimas) + TPM
Multi-WABA — AI Agent Impact
P14 · backlog-tier
Park RFC exists (draft) but unreviewed; no effort, no implementors. QA Lane B is driven by an out-of-reach trigger (external Meta WABA platform). Get the RFC reviewed; size and staff once reviewed. DRI (Dimas) + TPM
Meta Business Agent Integration
unranked · off-roadmap gap
Park Real 26Q3-targeted initiative (README + 3 phase PRDs exist) but missing from the roadmap Portfolio table (PORTFOLIO_MISSING) and absent from the Priority table — a roadmap-completeness gap, not an active commitment. No `jira_epic`, no RFC, no effort. Add a Portfolio row and a Priority rank (or explicitly defer past 26Q3), then start an RFC for Phase 1. TPM + DRI (Dimas)

01Capacity load — comfortable across the board; Baghiz is the lane to watch

Available-days: 65 eng-days/quarter × 0.8 focus = 52 effective (standard assumption, no per-person override recorded). Autonomous AI Agent Phase 2's BE (Farras+Eko, 8md combined) and FE (Samudra+Baghiz, 12md combined) are not itemized per person in the task-breakdown — split evenly below as a labeled assumption.

Baghiz FirdausaFrontend · autonomous, impact-report, testing
0.66 · 34.5 / 52 md
Tito AmandaQA · primary · autonomous, knowledge, impact-report, testing
0.46 · 24 / 52 md
Farras HerdichoBackend · autonomous, testing
0.39 · 20.5 / 52 md
Eko ApriantoBackend · autonomous, knowledge
0.23 · 12 / 52 md
Agus SuparmanBackend · impact-report
0.19 · 10 / 52 md
Samudra LinggarFrontend · autonomous, knowledge
0.14 · 7.5 / 52 md
IzzulQA · backup · knowledge, impact-report, testing
0.00 · 0 / 52 md (backup lane)
Capacity is not the constraint — sizing and external dependencies are No one is over. Baghiz is busiest at 0.66× (34.5md across three initiatives' FE tracks) — comfortable today but the one lane to watch if any of the three pulls forward at once. Tito is next at 0.46× QA across all four sized initiatives (the squad's only two QA people, Tito primary / Izzul backup, are on every one of them). Five of eight active/draft initiatives (Unified Agent Scorecard ×3, plus the whole backlog tier) remain entirely unstaffed — there is real headroom to pull that work in once its RFCs/estimates land.

02Per-initiative readiness

PInitiativeTargetStateEffort (md)Gates present
P1 Autonomous AI Agent — Phase 2 (Refiner)
Farras/Eko BE 8 · Samudra/Baghiz FE 12 · Tito QA 4.5
— (2026-Q3 window; Phase 1 100% done, sandbox-gated prod) Tentative 24.5 ·med PRD ✓ RFC ✓ Rev ✓ (8.5) · ~22.5md buildable now ·Data/ML endpoint ✗ date (Task 2.7 only)
P2 AI Agent Impact Report — Phase 1
Agus BE 10 · Baghiz FE 15.5 · Tito/Izzul QA 8
Do not commit 33.5 ·med PRD ✓ RFC ✓ Rev ✓ (8) ·design ✗ · Data/BI datamart ✗ date
P3 AI Agent Testing — Phase 1 (Historical Validation)
Farras/Baghiz BE+FE 16.5/13 · Tito/Izzul QA 8
Tentative 37.5 ·med-high PRD ✓ RFC ✓ Rev ✓ (8.5, 0 drift) ·AI platform capacity ✗ date
P4 AI Agent Knowledge — Phase 1 (Conversation History)
Eko/Samudra BE+FE 8/1.5 · Tito/Izzul QA 3.5
Do not commit 13 ·med PRD draft · RFC HOLD (7.5) · 4 blockers ✗
P5 Unified Agent Scorecard — Phase 1 (Settings & Rubric)
unstaffed
Park TBD PRD ✓ RFC ✓(draft, unreviewed) ·effort ✗ · design ✗ · unstaffed
P6 Unified Agent Scorecard — Phase 2 (Auto-Scoring)
unstaffed · depends on Phase 1
Park TBD PRD ✓ RFC ✗ · effort ✗ · design ✗ · unstaffed · DSAI contract ✗ date
P7 Unified Agent Scorecard — Phase 3 (Analytics Report)
unstaffed · depends on Phase 1/2
Park TBD PRD ✓ RFC ✗ · effort ✗ · Data/BI pipeline ✗ date
P8 Mekari Action (AI Agent)
unstaffed
— (no date; target_quarter 2026-Q3) Park TBD RFC ✗ · effort ✗ · unstaffed
P9 Native Integration (AI Agent) — Midtrans Phase 1
unstaffed
— (no date; target_quarter 2026-Q3) Park TBD RFC ✓ Rev ✓(7, notes) ·effort ✗ · unstaffed · REV-1/7 open
P10 Qontak Action (AI Agent)
unstaffed
— (no date; target_quarter 2026-Q3) Park TBD RFC ✗ · effort ✗ · unstaffed · PRD/README Epic drift
P11 AI Agent Idle Action (Sequential Idle Follow-up)
unstaffed
Park TBD RFC ✓ Rev ✓ (8.5) ·effort ✗ · unstaffed
P12 AI Agent Monitoring (Supervisor Alerts)
unstaffed
Park TBD RFC ✗ (PRD only) · effort ✗ · unstaffed
P13 Bot-vs-Human Traffic Split (A/B)
unstaffed
Park TBD RFC ✓(draft) ·Rev score ✗ · effort ✗ · unstaffed
P14 Multi-WABA — AI Agent Impact
unstaffed
Park TBD RFC ✓(draft) ·Rev score ✗ · effort ✗ · unstaffed
Meta Business Agent Integration
unstaffed · off-roadmap
Park TBD RFC ✗ · effort ✗ · no jira_epic · not on Portfolio/Priority tables

03Q3 timeline projection — mostly TBD by necessity, not by omission

Autonomous AI Agent has the only real, dated milestones (Phase 1 — 100% Jira done, production 2026-06-23, sandbox-gated / not GA) — and, new this pass, its Refiner (Phase 2) BE/FE/QA slices are now buildable with no date needed: per the task breakdown, chunks 1–8 run against a mocked/stub upstream, so Farras/Samudra/Baghiz/Eko/Tito can start today; only Task 2.7's real-upstream pass waits on Data/ML. Every other initiative's forward work is genuinely un-dateable today: three are sized but externally gated with no upstream date (or, for Knowledge, on an explicit HOLD), the rest are unsized/unstaffed. Capacity is not what's withholding a date — Farras/Eko/Samudra/Baghiz/Tito/Agus all have headroom; the remaining gates are external. Hatched grey = exists but undated; solid green = already shipped; solid blue/pink/teal = sized work buildable now (no external gate); dashed red lines mark the two known fixed dates in the whole portfolio (Data/AI's 2026-07-15 webhook + masking-SLA gates for AI Agent Knowledge).

Jul W1W2W3W4 Aug W5W6W7W8 Sep W9W10W11W12W13
Data/AI gates · 07-15
FarrasBE · autonomous, testing
Phase 1 BE — 100% done, sandbox prod
Refiner BE — build now (stub upstream)
Testing BE — externally gated, no start date
SamudraFE · autonomous, knowledge
Phase 1 FE — 100% done, sandbox prod
Refiner FE — build now (mocked BE)
Knowledge FE — on HOLD
BaghizFE · autonomous, impact-report, testing · 0.66×
Phase 1 FE — 100% done, sandbox prod
Refiner FE — build now (mocked BE)
Impact Report FE 15.5 + Testing FE 13 — sized, externally gated
EkoBE · autonomous, knowledge
Phase 1 BE — 100% done, sandbox prod
Refiner BE — build now (stub upstream)
Knowledge BE — on HOLD
AgusBE · impact-report · 0.19×
Impact Report BE 10 — sized, gated, no date
TitoQA · primary · autonomous, knowledge, impact-report, testing · 0.46×
Phase 1 QA — shipped
Refiner QA — build now (mocked BE)
Knowledge + Impact Report + Testing QA — 19.5md sized, all gated
IzzulQA · backup · knowledge, impact-report, testing
Backup lane — no window assignable yet
Shipped / done Buildable now — no external gate (mocked/stub upstream) Sized but externally gated / TBD start Known fixed gate date

04Schedule by initiative — start / end per discipline

Unlike a data-rich refresh, most rows below still read "gated, no date" — that is the honest state of the portfolio, not a rendering gap. The one exception is Refiner: nearly all of it is buildable now with no date needed. = shipped/in-flight now · ✓ building = sized work in progress, no external gate · = blocked, no date · = not yet staffed.

InitiativeBackendFrontendQA (Lane B)Lands
Autonomous AI Agent — Phase 2 (Refiner)
P1 · building now · Lane B
Farras + Eko
8md combined, unsplit — building now (mocked/stub upstream); only Task 2.7's real-upstream pass is blocked on Data/ML
Samudra + Baghiz
12md combined, unsplit — building now (mocked BE); same Task 2.7 tail blocked
Tito
4.5md sized — mocked-BE E2E/regression building now; only the real-upstream staging checklist trails Data/ML
✓ building, no date needed
Phase 1: 100% Jira done (80/80), production 2026-06-23 (sandbox-gated, not GA). Phase 2: ~22.5 of 24.5md executable today against the documented contract; only Task 2.7's real-upstream + config-audit pass is blocked on Data/ML — that portion alone has no date
AI Agent Impact Report — Phase 1
P2 · no date · Lane unclassified
Agus
10md sized, 0.19× load
Baghiz
15.5md sized, part of Baghiz's 0.66× combined load
Tito/Izzul
8md sized, part of Tito's 0.46× combined load
✗ unprovable
Effort reconciled (33.5md) and fully staffed; still no design, no date from Data/BI on the datamart dependency
AI Agent Testing — Phase 1 (Historical Validation)
P3 · no date · Lane B
Farras
16.5md sized — blocked on AI platform capacity, no date
Baghiz
13md sized — same block for Task 2.8; most other tasks startable
Tito / Izzul
8md sized — 11/13 tasks actionable now, 2 gated
✗ no date
Best-specified initiative in the portfolio (RFC review 8.5, zero drift); only missing an AI-platform-owned capacity date
AI Agent Knowledge — Phase 1 (Conversation History)
P4 · no date · Lane B
Eko
8md sized — 4/7 tasks actionable now (1.1/2.2/2.4/2.5)
Samudra
1.5md sized — gated on Figma frames (REV-2)
Tito / Izzul
3.5md sized
✗ HOLD
RFC review verdict is HOLD (7.5) — 4 blockers, 2 external (Data/AI, due 2026-07-15), 2 internal (design frames, scoping sign-off)
Unified Agent Scorecard — Phase 1 (Settings & Rubric)
P5 · no date · Lane B
TBD owner TBD owner TBD owner ✗ not staffed
No effort, no implementors, no design yet — concept prompts only
Unified Agent Scorecard — Phase 2/3
P6/P7 · no date · depends on Phase 1
TBD owner TBD owner TBD owner ✗ not staffed
Structurally can't start ahead of Phase 1; DSAI/Data-BI dependencies unresolved
Mekari / Native Integration / Qontak Action (backlog tier P8–P10)
no date · target_quarter 2026-Q3
TBD owner TBD owner TBD owner ✗ not staffed
Native Integration has a reviewed RFC (7); the other two have none. All three need a `target_quarter` re-baseline
Idle Action / Monitoring / Traffic Split / Multi-WABA (backlog tier P11–P14)
no date
TBD owner TBD owner TBD owner ✗ not staffed
Idle Action's RFC is execution-ready (score 8.5) but unstaffed; Monitoring has no RFC at all
Meta Business Agent Integration
unranked · off-roadmap
TBD owner TBD owner TBD owner ✗ not on roadmap
Not on Portfolio/Priority tables yet; no RFC, no jira_epic

05Schedule by PIC — what each person works on across Q3

One change this pass: Autonomous AI Agent Phase 1 is fully closed (100% Jira done, sandbox-gated production) and Refiner (Phase 2) is buildable now with no date needed — Farras, Samudra, Baghiz, Eko, and Tito can start their Refiner slices in July against a mocked/stub upstream. Everything else still reads the same: sized-but-gated or entirely unsized. building = in progress, no external gate · TBD = unsized work that exists but has no forecast.

PIC · roleJuly (W1–4)August (W5–8)September (W9–13)
Farras
BE · autonomous, testing
Refiner BE — building
Autonomous Phase 1 100% done (sandbox-gated prod) frees Farras for Refiner BE now — 8md combined w/ Eko, mocked/stub upstream; only Task 2.7's real-upstream pass trails Data/ML
Testing BE
16.5md — externally gated on AI platform capacity, no start date
Samudra
FE · autonomous, knowledge
Refiner FE — building
Autonomous Phase 1 100% done frees Samudra for Refiner FE now — 12md combined w/ Baghiz, mocked BE; only Task 2.7's real-upstream tail trails Data/ML
Knowledge FE
1.5md — on HOLD (4 blockers, Figma REV-2)
Baghiz
FE · autonomous, impact-report, testing · 0.66×
Refiner FE — building
6md half-split w/ Samudra, mocked BE, startable now; only the real-upstream tail (Task 2.7) trails Data/ML
Impact Report FE 15.5 + Testing FE 13
28.5md known-sized (busiest lane in the squad, still comfortably under 52 effective days) — Impact Report FE (sized, gated Data/BI + design), Testing FE (mostly actionable but gated on capacity date for full E2E)
Eko
BE · autonomous, knowledge · 0.23×
Refiner BE — building
Action-validation deploy (BOT-4357) now closed with the 100% Jira reconciliation; Eko moves onto Refiner BE — 8md combined w/ Farras, mocked/stub upstream, startable now
Knowledge BE
8md — 4/7 tasks actionable, but initiative is on HOLD
Agus
BE · impact-report · 0.19×
Impact Report BE 10md — sized
Blocked on Data/BI datamart — no date; sole assignment this quarter, well inside capacity
Tito
QA · primary · autonomous, knowledge, impact-report, testing · 0.46×
Phase 1 QA closed + Refiner QA — building
Action/Configuration/Tree-Diagram QA shipped 2026-06-17/18; Refiner QA (4.5md) mocked-BE E2E/regression drafting startable now — only the real-upstream staging checklist trails Data/ML
Knowledge + Impact Report + Testing QA
19.5md known-sized across the three initiatives, all gated on their respective external dependency — comfortably inside 52 effective days
Izzul
QA · backup · knowledge, impact-report, testing
No window assignable yet
Backup lane behind Tito's primary — nothing to schedule until Knowledge/Impact Report/Testing have dated E2E windows

06What blocks the lock

Cross-cutting constraints — the per-initiative gaps are in the decision table above.

  • Five 🔴 blocking cross-squad/external dependencies have no owner-committed date — Data/ML (Refiner's Task 2.7 real-upstream pass only — the rest of Refiner is building now), Data/BI ×2 (Impact Report, Scorecard Phase 3), AI platform ×2 (Testing, Scorecard Phase 2). Even the best-specified, best-staffed initiatives (Testing, Refiner, Impact Report) can't get a full forecast until these have dates — capacity is not what's holding them back.
  • Autonomous AI Agent Phase 1's production deploy (2026-06-23) is sandbox-gated, not GA — a hard-gate runtime error (`500 AUTONOMOUS_RUNTIME_ERROR`, legacy `NoneType` failures, open since 2026-06-03) blocks any client/CID enablement or GA claim, and no dedicated workstream is committed this sprint to close it — this is separate from, and does not block, Refiner's build-now status.
  • AI Agent Knowledge is on an explicit RFC-review HOLD (4 blockers) — the only initiative with a formal stop, not just an open dependency.
  • Fixed 2026-07-09: Four `target_quarter` drifts (`Mekari Action`, `Native Integration`, `Qontak Action` — backlog-tier P8–P10 — plus `Autonomous AI Agent`, whose README still said 2026-Q2 while its Phase-2 Refiner work ranks P1 in the 26Q3 order) were re-baselined to 2026-Q3. The roadmap `## Priority` table now carries a `priority_quarter: 2026-Q3` frontmatter field, and `lint-delivery.mjs` gained a `TARGET_QUARTER_STALE` warning so this class of drift is caught automatically going forward.
  • `meta-business-agent` is missing from the roadmap Portfolio/Priority tables despite being a live, PRD-bearing 26Q3 initiative — a roadmap-completeness gap the delivery linter already flags (`PORTFOLIO_MISSING`).

07Smallest path to "ready"

The few portfolio-level moves that unlock the most — in order.

  • Refiner is already unblocked for build — start Farras/Samudra/Baghiz/Eko/Tito on it now (Sprint 1 already reflects this); the only thing still needed is a Data/ML date for Task 2.7's real-upstream pass, which converts the last ~2md from Tentative → assessable.
  • Get an owner + ETA on the Autonomous AI Agent runtime-error hard gate (open since 2026-06-03) — this, not Data/ML, is what stands between the sandbox-gated deploy and Pilot/GA.
  • Get a date from the remaining 4 external/cross-squad owners (Data/BI ×2, AI platform ×2) — unblocks Testing, Impact Report, and Scorecard Phase 2/3. Capacity has headroom to absorb all of it once dated (busiest lanes, Baghiz FE 0.66× and Tito QA 0.46×).
  • Clear AI Agent Knowledge's 4 HOLD blockers — two are external gates already due 2026-07-15; chasing those two first may resolve the HOLD without waiting on the internal design/sign-off pair.
  • Start AI Agent Impact Report's Figma design track — effort and staffing (Agus BE, Baghiz FE, Tito/Izzul QA) are both resolved; design is the one gap left that's inside the squad's control.