Chatbot - Sprint 02 Goals (2026-Q3)

Delivery / Program Management - team-level, cross-initiative. A sprint is a derived render of the roadmap Priority table x per-discipline implementors: x each initiative's rfcs/*.task-breakdown.md readiness x capacity.md, plus the sprint envelope above. It is not a source of truth for priority, effort, or staffing - those stay canonical in the roadmap / README / capacity. See CLAUDE.md "Sprint layer".

Sprint window: 2026-07-27 -> 2026-08-10 (2 weeks)

Sprint goal: convert Sprint 1's 28-item in-flight tail into shipped, code-evidenced work; give P2 AI Agent Impact Report its first implementation queue by starting the unblocked mock-first FE phase; and close the two gaps that stop the board telling the truth — P5's missing task breakdown and the unmodeled 26Q3 Fast-track lane.

Source (derived from): the ## Priority table and ## Adhoc / Interrupt lane in ../roadmap.md, the staffing mirror in ../capacity.md, recorded initiative implementors: / qa:, the available task breakdowns, and — for carry-forward — sprint 01's findings ledger and pass 16.

Carry-forward caveat. This sprint opens on the day sprint 01 closes (2026-07-27), matching sprint 01's Monday-to-Monday boundary convention. Sprint 01 closed at pass 16 with 12 findings open or escalated. No item is carried by default: every row below was re-derived from current roadmap rank and its breakdown's remaining work.

Completion updates — 2026-07-27​

CRM Deals Custom Fields (P10 / BOT-4662) reached General Availability effective 2026-07-27 — see status 2026-07-27.

Sprint 2 outcome targets​

  1. The in-flight tail lands. 28 items entered this window mid-flight — 6 Ready to Merged, 5 In Deployment, 9 In Testing, 4 In Progress, 2 In Review. Landing them, with merged-code evidence, is the first call on every queue and outranks starting new slices.
  2. P2 AI Agent Impact Report gets implementation tickets and starts. The rank-2 initiative has carried an escalated coverage-gap (F-2/F-42) since sprint 1: 1 board issue, 0 BE/FE, against a complete 33.5d / 19-task breakdown. Phase 1 (FE, mocked, 13d) has no external gate — file it and start it.
  3. P3's progress number becomes true. A 7% floor is now recorded (status 2026-07-27); resolve the F-14 descope and the F-52 breakdown join that cap it.
  4. P5's planning gap closes. Unified Agent Quality Scorecard Phase 1 still has no task breakdown and no implementors: — the one sprint-1 outcome target that did not move. (P4's breakdown did land, closing the other half.)
  5. The 26Q3 Fast-track lane gets modelled or explicitly rejected. Epic BOT-4554 holds live production-bug work and maps to no initiative and no bucket in this repo. It is consuming real capacity invisibly.

Initiative index​

All paths are relative to this file. Priority ranks come from the roadmap ## Priority table.

PriInitiative (Epic)Sprint 2 roleReady basis / effort contextBuild gate
P1Autonomous AI Agent - Phase 2: AI-Assisted Refinement (BOT-4602)Finish + close — all 6 BE/FE issues Done; QA is the only remainderbreakdown: 24.5d (FE 12, BE 8, QA 4.5); README progress_pct: 51None remaining for BE/FE; QA evidence outstanding
P2AI Agent Impact Report - Phase 1: Live Impact Report (BOT-4568)Primary new-build track — file implementation tickets, start mock-first FEbreakdown: 33.5d (FE 15.5, BE 10, QA 8); Phase 1 FE 13d ungatedData/BI datamart + OQ-1/OQ-2/REV-2 gate Phase 2 only
P3AI Agent Testing - Phase 1: Historical Validation (BOT-3351)Land the tail + make progress truebreakdown: 37.5d (FE 13, BE 16.5, QA 8); 7 items in flightAI platform batch capacity; F-14 descope decision
P4AI Agent Knowledge - Phase 1: Conversation History (BOT-3992)Start mocked FE + unblocked BE contract slicesbreakdown now exists (new since sprint 1): 30.5d (FE 7, BE 16, QA 7.5) — conflicts with README 13d, see blockersData & AI masking/training/webhook contracts gate Tasks 2.4–2.9
P5Unified Agent Quality Scorecard - Phase 1: Settings & Rubric (BOT-4573)Planning gap — close itstill no task breakdown; no implementors: recordedFE design frames; DSAI rubric wording (non-blocking for Phase 1 per its PRD)
P6Unified Agent Quality Scorecard - Phase 2: Auto-Scoring & In-Room (BOT-4573)Visible backlog onlynot projected into Sprint 02Not pulled unless PM/TPM explicitly reprioritizes
P7Unified Agent Quality Scorecard - Phase 3: Analytics Report (BOT-4573)Visible backlog onlynot projected into Sprint 02Not pulled unless PM/TPM explicitly reprioritizes
P8Mekari Action (AI Agent) (BOT-4571)Visible backlog onlynot projected into Sprint 02Not pulled unless PM/TPM explicitly reprioritizes
P9Native Integration — Google Calendar Phase 1 (BOT-4482; umbrella BOT-4600)Land + evidence the sprint-1 Goal-1 sliceeffort still TBD; 3 items in flight (1 FE merge-ready, 2 QA in testing)Google app verification is external — never represent as approved
P10Qontak Action — CRM Deals Custom Fields (BOT-4662; umbrella BOT-4597)Landed / GA — close evidence reconciliation onlyGA effective 2026-07-27 — see status 2026-07-27F-26: BOT-4668 descoped; BOT-4669/4673 remain board-Done without code trace
P11AI Agent Idle Action (BOT-4567)Visible backlog onlynot projected into Sprint 02Not pulled unless PM/TPM explicitly reprioritizes
P12AI Agent Monitoring (BOT-4569)Visible backlog onlynot projected into Sprint 02Not pulled unless PM/TPM explicitly reprioritizes
P13Bot-vs-Human Traffic Split (A/B) (BOT-4570)Visible backlog onlynot projected into Sprint 02Not pulled unless PM/TPM explicitly reprioritizes
P14Multi-WABA Impact (BOT-4572)Visible backlog onlynot projected into Sprint 02Not pulled unless PM/TPM explicitly reprioritizes
—Chatbot 26Q3 Engineering Initiatives (bucket, Epic BOT-4620)Per-story pull — A1 in flight, A4 closing, A6 newly pulledtracker; classed not rankedPer-story; A1 Expedite authorization still TBD
—Chatbot Q3 2026 Code Readiness (bucket, Epic BOT-4500)Per-story pull — A5 in progresstracker; classed not rankedPer-story; open-contributor

Per-engineer queues​

Each person works their list top-to-bottom. A genuinely blocked item is skipped and revisited once the blocker clears. Queue order mirrors roadmap priority except where listed in ## Deviations from roadmap priority.

Sprint-wide rule this window: an item you already have in flight outranks a new slice. Land it, merge it, and make sure the Jira key appears in a commit on the default branch — pass 16 found 12 of 30 done issues unmerged and 9 with no trace at all, and unevidenced "done" buys the team nothing.

Farras Herdicho (BE)​

Agent brief: start at row 1 and get all four P3 branches merged to origin/master before touching anything else — Linggar's two In-Deployment FE items and Tito's QA sit behind them. Skip row 3 if the board has already been corrected. You unblock P3's entire close-out.

#Epic (Jira)TaskStatus
1AI Agent Testing (BOT-3351, P3)Land the 4 in-flight BE items: BOT-4619 (Task 2.3 gap — rating PATCH + transactional recompute), BOT-4723 (stale-question daily cron), BOT-4728 / BOT-4729 (list/detail adjust)Ready — all 4 Ready to Merged; BOT-4619 is the oldest WIP on the board (~13d)
2Code Readiness (BOT-4500, bucket story A5 🟡)CR-S05 Internal Tooling Improvement (BOT-4742) — in-progress per trackerReady · Pull rule verdict PULL-TO-CLOSE — 🟡 Standard, single-discipline BE, closeable in-window
3Code Readiness (BOT-4500, P—)Board correction for F-27: BOT-4655, BOT-4656, BOT-4658 are done/Won't Fix with zero code trace on any ref — merge the work or correct the boardReady — a board fix, never a repo edit
4AI Agent Testing (BOT-3351, P3)Next unstarted BE tasks from the breakdown once rows 1–3 clearReady from breakdown; execution gated on AI platform batch capacity

Samudra Linggar (FE)​

Agent brief: clear the remaining in-flight FE items in row 1 first. Row 1 is verification and release, not new code; the CRM Custom Fields slice (BOT-4725) is already done in FE 3.8.4. Then close engineering bucket story A4. Only then start P4's mocked FE — it is genuinely unblocked because Phase 1 mocks the Data & AI contracts.

#Epic (Jira)TaskStatus
1aAI Agent Testing (BOT-3351, P3)Land BOT-4697 + BOT-4732 (Testing FE port + modal/flag gate)Ready — In Deployment; verification + release
1bCode Readiness (BOT-4500, bucket)Land BOT-4657Ready — In Deployment
1cEngineering Initiatives (BOT-4620, bucket)Land BOT-4736 (reasoning value not saved)Ready — In Deployment
1dQontak Action — CRM Deals Custom Fields (BOT-4662, P10)BOT-4725 (QACF TypeError) — completed in FE 3.8.4Done — passed QA and released
2Engineering Initiatives (BOT-4620, bucket story A4 🟡)Subscription feature-flag gating reliability — BOT-4696, in-reviewReady · Pull rule verdict PULL-TO-CLOSE — 🟡 Standard, FE-only, already in review. Note: A4 is a placeholder story with no RFC, reconstructed from BOT-4650 code changes
3AI Agent Knowledge (BOT-3992, P4)Start Phase 1 mocked FE from the new breakdown: Task 1.1 (entry + service contract), 1.2 (configuration form), 1.3 (training-status states + source detail) — FE 6dReady — Phase 1 mocks the Data & AI contracts, so it is not gated
4Autonomous AI Agent Phase 2 (BOT-4602, P1)FE complete — support Tito's QA close-out onlyNo remaining FE build

Baghiz Firdausa (FE)​

Agent brief: clear the remaining merge-ready items in row 1 first; the CRM Custom Fields slice is already closed (BOT-4724 done, BOT-4727 re-parented/done). Row 2 is the sprint's headline new build and the tickets do not exist yet: do not start until sprint-jira-sync has filed them, or the work will be invisible to the board exactly as it was in sprint 1. Tasks 1.1–1.8 are mock-first; never fabricate a datamart field.

#Epic (Jira)TaskStatus
1aAI Agent Knowledge (BOT-3992, P4)Land BOT-4734 (save — page unresponsive). Epic cited is where the docs say it belongs; on the board it is unparented — parenting is a PM/TPM fix, see Deviations + blocker 6Ready — Ready to Merged
1bNative Integration — Google Calendar (BOT-4482, P9)Land BOT-4735 (Google Calendar icon)Ready — Ready to Merged
1cQontak Action — CRM Deals Custom Fields (BOT-4662, P10)BOT-4724 (QACF field picker) — completed; BOT-4727 completed under Get Ticket & Get Deals Epic BOT-4790Done — QACF slice closed
2AI Agent Impact Report (BOT-4568, P2)Sprint 2 headline: Phase 1 mock-first FE, breakdown order — Task 1.1 (Pinia store/service/fixtures), 1.2 (feature+role gate middleware), 1.3 (report shell + baseline-forming + error/retry), 1.4 (value-delivered tiles), then 1.5–1.8 (quality tiles, BlendedJourneyBar, ForecastPanel, CostAssumptionModal). FE 13dBlocked on ticket creation, not on engineering — F-2/F-42: zero BE/FE issues exist under BOT-4568. Run sprint-jira-sync first. Use placeholder constants for OQ-1/OQ-2
3AI Agent Testing (BOT-3351, P3)FE work from the breakdown (13d) behind Linggar's port landingReady from breakdown
4Code Readiness (BOT-4500, bucket A2/A4 🟡)CR-S02 testing improvement, CR-S04 agent skills (with Linggar)Pull rule verdict BE-advance → defer — 🟡 Standard, both backlog, not closeable alongside rows 1–3

Eko Aprianto (BE)​

Agent brief: row 1 is live production work you already hold — finish it, but see Deviations: it sits under an Epic this repo does not model, so log what you spend. Row 2 is a board-truth fix, not a feature. Row 3 is your real build lane, and only Tasks 2.1–2.3 are startable. Row 5 is a new bucket story pulled 2026-07-27, adjacent to your row-1 ticket.

#Epic (Jira)TaskStatus
126Q3 Fast track (BOT-4554)BOT-4746 — AI Resource Upload stuck in Processing statusIn progress — unmodeled lane; see ## Deviations and blocker 6
2Qontak Action — CRM Deals Custom Fields (BOT-4662, P10)F-26 evidence reconciliation: BOT-4668 is Won't Fix/descoped; BOT-4669 and BOT-4673 remain board-done without merged-code evidence — correct the board truthDone for rollout — corroborated in status 2026-07-27; board-truth follow-up remains
3AI Agent Knowledge (BOT-3992, P4)Start the ungated BE contract slices from the new breakdown: Task 2.1 (division scope on sources), 2.2 (divisions+agents directory endpoint), 2.3 (extend create contract)Ready — Tasks 2.4–2.9 (delete guard, sync worker, webhook consumer, masking/quality gate, room-link contract) stay blocked on Data & AI
4AI Agent Testing (BOT-3351, P3)BE support; note capacity records him as Jira-assigned here (BOT-3942) without a sized allocationReady; sequencing behind Farras
5Engineering Initiatives (BOT-4620, bucket story A6 🟡)Alert detecting an AI knowledge upload stuck in Processing >5h — BOT-4796, To Do → context noteReady · Pull rule verdict PULL-TO-CLOSE — 🟡 Standard, single-discipline BE, closeable in-window

Agus Suparman (BE)​

Agent brief: your two Ruby/Rails items are the oldest in-progress work on the board (~13 days) — land them first. Row 2 is P2's backend, and only Task 2.1 is genuinely startable; do not invent datamart fields to unblock 2.2/2.4/2.6.

#Epic (Jira)TaskStatus
1Engineering Initiatives (BOT-4620, bucket story A1 🔴 Expedite)Land Ruby 3.4 / Rails 7.2 Phase 1 tail: BOT-4635 (Task 13 — aegis boot spike, In Review) and BOT-4636 (Task 14 — staging bake + dual-cloud canary, In Progress) — per Phase 1 RFC + breakdownReady · PULL-TO-CLOSE — 🔴 Expedite, WIP limit 1 respected; oldest WIP on the board (~13d). Tracker and Expedite-authorization drift: see Deviations
2AI Agent Impact Report (BOT-4568, P2)BE Phase 2 from the breakdown — start Task 2.1 only (migrations for ai_activity_logs + ai_cost_assumptions + rooms indexes, incl. the REV-4 scan-cost risk)Partially ready — Task 2.2 (aggregator correctness core, REV-1/REV-3), 2.4 (entitlement, OQ-1/OQ-2), 2.6 (forecast, REV-2/OQ-10) all blocked on Data/BI + open RFC questions
3Native Integration — Google Calendar (BOT-4482, P9)Assemble the Google OAuth app-verification technical inputs: scope justification, demo environment, consent/branding evidenceReady for prep — submission and approval are external and owned by Google
4Engineering Initiatives (BOT-4620, bucket story A2 🟡)Phase 2 Rails 8.1 discoveryPull rule verdict defer — 🟡 Standard, backlog, not closeable while A1 is in flight

Tito Amanda (QA)​

Agent brief: you are the sprint's bottleneck — 9 items sit In Testing across 6 Epics. Work rows 1a–1c in that order (P9 Goal-1 carry-over, then P1 close-out, then BAU), and raise it early if the queue cannot clear: several initiatives cannot be called done without your evidence.

#Epic (Jira)TaskStatus
1aNative Integration — Google Calendar (BOT-4482, P9)BOT-4642 — test the Google OAuth app-registration flow and record the verification evidence; Dimas Fauzi Hidayat helps with the actual registration/submission after the evidence is readyTo Do — Tito owns QA testing and recording; Google's verification decision is not a sprint test result
1bAutonomous AI Agent Phase 2 (BOT-4602, P1)BOT-4644 — Refiner test-case creation. This is the only thing between P1 and doneIn testing
1cAI Agent Testing (BOT-3351, P3)BOT-4646 — Historical Validation test-case creationIn testing
2AI Agent Impact Report (BOT-4568, P2)BOT-4645 — test-case creation; then QA the mocked FE flow as Baghiz lands Tasks 1.1–1.8In testing — data correctness waits on the BE/Data contract
3QA BAU (BOT-4609; ../qa-bau.md)Land the 4 in-flight BAU items: BOT-4638 (test-case mgmt migration Pt.2), BOT-4639 (delivery maintenance automation), BOT-4647 (Sprint 1 deployment verification), BOT-4648 (P0 coverage web+API)In testing — scheduled deployment verification takes precedence
4Qontak Action (BOT-4662, P10)BOT-4688 — QACF QA across S01–S04Done — coverage completed; no QA man-days estimated

Izzul (QA, backup)​

Agent brief: short queue by design — you are backup QA. Row 2 is a five-minute board fix that clears a standing reconciliation finding, so do it even though it isn't test work.

#Epic (Jira)TaskStatus
1QA BAU (BOT-4609)BOT-4637 — Sprint 1 automation-coverage increase, In ReviewReady
2QA BAU (BOT-4609)Reparent BOT-4461 ("Increase Coverage P0 Automation Test WEB") from BOT-3972 to BOT-4609. BOT-3972 is the 26Q2 BAU Epic and is itself Done — this is the quarter rollover qa-bau.md describesReady — closes the last live part of F-41
3Product initiativesBackup QA for Tito's queue on request; capacity records 0 committed daysReady on demand

How to point your AI agent at this plan​

Copy-paste brief:

You are working the Chatbot 26Q3 Sprint 2 plan at chatbot/delivery/sprints/2026-07-27-sprint-02.md. Find your engineer's ### <Name> section, read the Agent brief, and work the numbered queue top-to-bottom. For each row, the task breakdown linked from the Initiative index is the work contract — read the task's What to build, Implementation steps, Acceptance criteria, and Run to verify before writing code. Stop and ask if a row's gate is still closed.

Ground rules:

  • The task breakdown is the contract. Do not re-derive scope from the PRD or from this sprint doc; this doc only says which tasks and in what order.
  • Man-days are sequencing context, never a cap or a deadline. Capacity lives in ../capacity.md.
  • A Jira key must reach the default branch. Put the key in your branch name and commit messages. Reconciliation counts merged code, not board status: 21 of sprint 1's 30 done issues were uncorroborated and contributed 0 man-days.
  • Never touch the jira-sync / main-full automation. Board items for this sprint are filed by sprint-jira-sync (manual, per-user-story). The per-AC pipeline is a different convention and pointing it at these Epics would create duplicate Stories.
  • Do not invent contract fields. Where a row says blocked on Data/BI, Data & AI, or an OQ, use a clearly-labelled placeholder and leave the gate visible.
  • Do not renumber a published AC or story id. It re-keys its Jira ticket.

Deviations from roadmap priority​

  • Landing the in-flight tail outranks rank this window. 28 items entered the sprint mid-flight and every queue starts with them, so lower-ranked work (P9, P10, buckets) appears above higher-ranked new build in several queues. This is sequencing on state, not a reprioritization — the roadmap order is unchanged. It should not persist beyond this window; if it does, the tail is structural and belongs in a decisions/ ADR.

    The seven specific rank inversions this produces (each raises an advisory SPRINT_QUEUE_ORDER in lint:delivery — all intentional, enumerated here so none is silent):

    QueueInversionWhy
    Samudra Linggar (FE)P1 below P4P1 has no remaining FE build — all 6 BE/FE issues are Done. Its row is a support note for Tito's QA close-out, so it sits last by nature, not by deprioritization.
    Eko Aprianto (BE)P4 below P10The P10 row is now rollout-complete evidence reconciliation (F-26: BOT-4668 is descoped; BOT-4669/4673 remain board-done without code), not feature work. The GA record is complete; only board truth remains.
    Eko Aprianto (BE)P3 below P4P3 BE is sequenced behind Farras's four merges (his row 1). P4 Tasks 2.1–2.3 are startable now; P3 support is not.
    Tito Amanda (QA)P1 below P9Sprint-Goal-1 Google Calendar QA is carried over from sprint 1 and was already a documented deviation there. Same reason, one window later.
    Tito Amanda (QA)P2 below P3Both are In Testing; P3's test-case creation gates P3's close-out this window, while P2's gates a build that has not started (no tickets exist).
    Baghiz Firdausa (FE)P2 below P102026-07-27, from the row-1 split: rows 1a–1c were tail-first completion work; the QACF slice is now closed (BOT-4724 done, BOT-4727 re-parented/done) while P2 has no tickets to start (F-2/F-42).
    Samudra Linggar (FE)P4 below P102026-07-27, from the row-1 split: rows 1b–1d were tail-first release verification; QACF BOT-4725 is now done in FE 3.8.4, not new build.
  • 2026-07-27: the two Epic = Multiple tail rows were split one-row-per-Epic. Samudra Linggar's and Baghiz Firdausa's row 1 each bundled a mid-flight batch spanning four Epics under a Multiple Epic cell. Multiple joins to nothing in the ## Initiative index, so sprint-drift-audit could not attribute those 9 items to an initiative or rank, lint:delivery Group I could not check their queue order, and their merged-code evidence had no initiative to roll up to at close — precisely the items most likely to drift. They are now rows 1a–1d / 1a–1c, each carrying its real Epic key, kept contiguous at the top so the tail-first rule still reads. The two inversions this made visible are in the table above. No scope, staffing, or rank changed.

  • Three SPRINT_EPIC_DRIFT advisories are expected under the umbrella model. Autonomous (BOT-4602 ≠ README BOT-4601), Native Integration (BOT-4482 ≠ BOT-4600), and Qontak Action (BOT-4662 ≠ BOT-4597) each cite the child Epic where Stories/Tasks actually hang. Do not resolve these by collapsing rows onto an umbrella anchor — see the ## Initiative index comment.

  • P2 (rank 2) starts implementation only now, in sprint 2. It has been ranked since 2026-07-02 with a complete 33.5d breakdown and has never had a single BE/FE ticket. This is the standing escalated finding F-2/F-42, not a planning choice — recorded here so the delay is visible rather than re-absorbed. Ticket creation is a prerequisite for Baghiz's row 2.

  • P4 gets a real build queue while P5 does not. P4's task breakdown landed during sprint 1; P5's still does not exist and P5 has no implementors:. This follows readiness, not rank — P5 remains limited to breakdown generation and staffing.

  • The 26Q3 Fast-track lane is NOT rendered as queue rows. Epic BOT-4554 carries three live In-Progress production bugs (BOT-4739 — Dhita Putri Pratama, BOT-4746 — Eko, BOT-4741 — unassigned). It maps to no initiative and no bucket in this repo, so per doctrine it is flagged to the PM for scoping, not invented into a plan. Eko's row 1 records only the item he already holds. Two knock-ons: Dhita Putri Pratama is not in roster.json or capacity.md at all (F-46), and BOT-4734 (Baghiz) has no parent Epic — both need a PM/TPM decision this window.

  • Engineering bucket A1's tracker status contradicts the board. The tracker rows A1 as backlog while Tasks 13–14 are In Review/In Progress and Tasks 1–12 are already board-done. The bucket's ## Expedite log also still shows Authorized by: TBD for a 🔴 Expedite that has been executing for two weeks. Both are tracker-truth fixes owed by the DRI; this sprint renders the verdict and does not re-class the story.

  • P6–P14 remain backlog-visible only. Pulling lower-ranked work into Sprint 2 requires an explicit PM/TPM decision and should be reflected in the roadmap or a delivery decision if it persists.

Adhoc interrupts (this sprint)​

One 🔴 Expedite is in flight, rendered from the bucket tracker — not originated here:

Bucket (Epic)StoryClassOwnerStateVerdict (from Pull rule)
Chatbot 26Q3 Engineering Initiatives (BOT-4620)A1 — Ruby 3.4 / Rails 7.2 Phase 1🔴 ExpediteAgus (BE), Tito+Izzul (QA)Tasks 13–14 in flight, ~13d oldPULL-TO-CLOSE — finish in this window; WIP limit 1 respected, no second Expedite may enter

The 26Q3 Fast-track lane (BOT-4554) is deliberately absent from this table: it is not a declared bucket, so it has no Class-of-Service, no Pull rule, and no WIP limit to render. See Deviations.

The real blockers (not capacity)​

  1. P2 AI Agent Impact Report — no implementation tickets exist. The nearest-term blocker is internal, not external: 0 BE/FE issues under BOT-4568 (F-2/F-42, escalated since sprint 1). Ask: TPM/DRI to run jira-alignment-check then sprint-jira-sync before Baghiz's row 2 starts.
  2. P2 Phase 2 — Data/BI ai_activity_logs datamart + open RFC constants. Ask: confirm fields, per-org aggregation rules, freshness, access path, owner, AI add-on feature code (OQ-1), canonical FE role strings (OQ-2), after-hours source, and the forecast algorithm (REV-2/OQ-10).
  3. P3 AI Agent Testing — AI platform batch shadow-inference capacity, plus the F-14 descope decision: BOT-3949/4616/4617/4618 are Won't Fix with no code, and three of them are the only breakdown-joinable done tasks besides Task 2.4. Until the descope is confirmed, P3's progress is capped at the recorded 7% floor. Ask: assignee/DRI + Dimas to confirm descope and cut the 37.5d baseline, or correct Jira.
  4. P4 AI Agent Knowledge — Data & AI contracts (PII masking, training/vector service, training-status webhook) gate Tasks 2.4–2.9. Ask: confirm payloads, retry semantics, 90-day rolling sync, source lifecycle, and masking SLA.
  5. P4 effort figures now conflict. The new breakdown totals 30.5d (FE 7 / BE 16 / QA 7.5) while the README and capacity.md still carry 13d (FE 1.5 / BE 8 / QA 3.5) — a 17.5-day gap on a ranked initiative. Ask: DRI to reconcile the canonical README effort_*_days against the breakdown and re-mirror to roadmap + capacity, then lint:delivery.
  6. 26Q3 Fast-track lane (BOT-4554) is unmodeled. Three live production bugs, one unassigned, one held by a person absent from the roster. It consumes capacity invisibly and cannot be reconciled. Ask: PM/TPM to declare it (a bucket initiative with a Class-of-Service tracker, or an explicit out-of-scope support lane), add Dhita Putri Pratama to roster.json + capacity.md, assign BOT-4741, and give BOT-4734 a parent.
  7. P5 Unified Agent Quality Scorecard — no task breakdown, no implementors. The one sprint-1 outcome target that did not move. DSAI rubric wording is explicitly non-blocking for Phase 1 per its own PRD, so this gap is internal. Ask: DRI/TPM to generate the breakdown and name implementors.
  8. P9 Google Calendar — external app verification. Production Cloud project, exact redirect URI, authorized-domain ownership, consent-screen links/contacts, least-privilege scope justification, and an English demo video. Sensitive-scope verification is Google's decision; testing proves readiness and cannot guarantee approval.

Sprint review​

  • Shipped / done: TBD at close.
  • Carried over: TBD.
  • Added mid-sprint: TBD.
  • Fed into status: the status/<date>.md reports updated with this sprint's progress (link them).
  • Decisions taken: link any delivery/decisions/ ADR + roadmap Priority reorder this sprint triggered.