Qontak Action (AI Agent) — Status 2026-07-20
Delivery / Program Management — periodic status report. Source:
sprint-drift-auditpass 8 (reconciliation).
Summary
CRM Deals Custom Fields (child Epic BOT-4662) BE execution is nearly complete: 4 of 6 breakdown
man-days corroborated done (Tasks 3/4/5 merged; Task 1 Won't Fix). progress_* stays 0 because
the README effort_* baseline is still TBD (umbrella initiative, no aggregate sizing) — no
percentage is computable; the evidence is recorded here so nothing is lost.
Metrics
- BE (breakdown
crm-actions-custom-fields.task-breakdown.md, 6 md total): Done + code-corroborated onchatbotorigin/master— Task 3 BOT-4670 (PR #2394, 1.5 md), Task 4 BOT-4671 (PR #2397, 2 md), Task 5 BOT-4672 (PR #2395, 0.5 md) = 4 md. Task 1 BOT-4668 Won't Fix (0.5 md descoped — DRI to confirm). - Board-done, no code trace (pass-8 finding F-26, excluded): Task 2 BOT-4669
(
AdditionalFieldNormalizer— no commits and no file onorigin/master) and Task 6 BOT-4673 (node-registry seed). Either genuinely superseded/code-free (state it) or stale board status. - FE: BOT-4680–4683 in progress (0 md by rule); QA BOT-4688 To Do.
- Baseline gap: README
effort_total_days: TBDblocks theprogress_pctmath — DRI/PM to size the initiative (or the BOT-4662 slice) so the next pass can capture percentages.