Qontak Action (AI Agent) — Status 2026-07-23

Delivery / Program Management — periodic status report. Source: sprint-drift-audit pass 9 (reconciliation).

Summary

CRM Deals Custom Fields (child Epic BOT-4662) BE execution is essentially complete on the board: 3.0 of 5.0 breakdown man-days corroborated done (Tasks 3/4/5 merged), FE 6/6 tasks board-Done. progress_* stays 0 because the README effort_total_days baseline is still TBD (umbrella initiative, no aggregate sizing) — no percentage is computable; the evidence is recorded here. This initiative is engine-blind: sprint:reconcile's code-evidence join excludes off-map umbrella-child Epics, so BOT-4662 done issues get no automated verdict — the numbers below are a manual git join (report the exclusion upstream to sprint-reconcile.mjs).

Metrics

  • BE (breakdown crm-actions-custom-fields.task-breakdown.md, 5.0 md BE total): Done + code-corroborated on chatbot origin/master — Task 3 BOT-4670 (PR #2394, 1 md), Task 4 BOT-4671 (PR #2397, 1.5 md), Task 5 BOT-4672 (PR #2395, 0.5 md) = 3.0 md. Task 1 BOT-4668 Won't Fix (0.5 md descoped — DRI to confirm).
  • Board-done, no code trace (finding F-26, ⛔ escalated 2nd pass, excluded from the sum): Task 2 BOT-4669 (AdditionalFieldNormalizer) and Task 6 BOT-4673 (node-registry seed) — zero commits in chatbot/chatbot-fe (any ref), while sister tasks merged, so the gap is specific. Either genuinely superseded/code-free (state it) or a stale board status. Owner: Eko Aprianto.
  • FE (7 md total): BOT-4680–4683/4699/4722 all board-Done; corroboration deferred (chatbot-fe not exhaustively joined this pass) — 0 md credited until confirmed, by rule.
  • Baseline gap (unchanged from pass 8): README effort_total_days: TBD blocks progress_pct — DRI/PM to size the initiative (or the BOT-4662 slice) so a future pass can capture percentages.